5138 S HILLCREST DR 90043

Certificate Information: 5138 S HILLCREST DR 90043

Application / Permit
23016-30000-15368
Plan Check / Job No.
B23WL01240
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) detached garage into an (N)ADU and addition per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33 (c),(d) and (g)
Permit Issued
Issued on 9/25/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2023 APPLICANT
Assigned to Plan Check Engineer 5/18/2023 RICHARD GARCIA
Corrections Issued 5/18/2023 RICHARD GARCIA
Building Plans Picked Up 5/26/2023 APPLICANT
Applicant returned to address corrections 9/18/2023 JOHNPAUL ISIP
Plan Check Approved 9/22/2023 CAROLEAN BASMA
Issued 9/25/2023 APPLICANT
CofO in Progress 6/21/2024 ANTHONY EGSON
CofO Issued 7/9/2024 DEROLD HAUFF
Permit Finaled 7/9/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/3/2023 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 7/12/2023 JESSICA OPINION
Sewer availability Cleared 7/12/2023 JESSICA OPINION
Low Impact Development (LID) Cleared 9/13/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 9/19/2023 NEIL TUANO

Contact Information

Contractor Owner-Builder       ,
Engineer Namvar,, Mohammad Alipour; Lic. No.: C39797 231 VISTA DEL MAR STE D      REDONDO BEACH, CA 90277

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/7/2023 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 11/17/2023 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 11/29/2023 Approved ANTHONY EGSON
Reinforced Concrete Frame 11/29/2023 Not Ready for Inspection ANTHONY EGSON
Footing/Foundation/Slab 12/11/2023 Partial Approval ANTHONY EGSON
Insulation 12/11/2023 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 12/18/2023 Partial Approval ANTHONY EGSON
ELECTRICAL-Rough 12/27/2023 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 12/27/2023 Approved ANTHONY EGSON
PLUMBING-Rough 12/27/2023 Partial Approval ANTHONY EGSON
ELECTRICAL-Rough 1/2/2024 Approved ANTHONY EGSON
Gas Test 1/2/2024 Partial Approval ANTHONY EGSON
Interior/Exterior Lathing 1/2/2024 Approved ANTHONY EGSON
ELECTRICAL-Rough 1/8/2024 Approved ANTHONY EGSON
HVAC-Rough 1/8/2024 Approved ANTHONY EGSON
Insulation 1/12/2024 Approved STUART CHAPMAN
Drywall Nailing 1/24/2024 Approved ANTHONY EGSON
Interior/Exterior Lathing 1/29/2024 Approved ANTHONY EGSON
Underground Mechanical 3/20/2024 Approved ANTHONY EGSON
Underground Mechanical 3/21/2024 Partial Approval ANTHONY EGSON
Underground Mechanical 3/22/2024 Corrections Issued ANTHONY EGSON
Sewer 3/29/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 4/5/2024 Corrections Issued ANTHONY EGSON
HVAC-Final 4/15/2024 Approved ANTHONY EGSON
PLUMBING-Final 4/17/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 5/17/2024 Approved ANTHONY EGSON
Final 5/17/2024 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 5/17/2024 Approved ANTHONY EGSON
Green Building Final 5/17/2024 Approved ANTHONY EGSON
Green Building Rough 5/17/2024 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 5/17/2024 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 5/17/2024 Approved ANTHONY EGSON
Final 5/28/2024 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 5/28/2024 SGSOV Approved ANTHONY EGSON
ELECTRICAL-Final 6/20/2024 Approved ANTHONY EGSON
Final 6/20/2024 OK to Issue CofO ANTHONY EGSON
Service/Power Release 6/20/2024 Approved ANTHONY EGSON