5138 S HILLCREST DR 90043
Certificate Information: 5138 S HILLCREST DR 90043
- Application / Permit
- 23016-30000-15368
- Plan Check / Job No.
- B23WL01240
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached garage into an (N)ADU and addition per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33 (c),(d) and (g)
- Permit Issued
- Issued on 9/25/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2023 | RICHARD GARCIA |
| Corrections Issued | 5/18/2023 | RICHARD GARCIA |
| Building Plans Picked Up | 5/26/2023 | APPLICANT |
| Applicant returned to address corrections | 9/18/2023 | JOHNPAUL ISIP |
| Plan Check Approved | 9/22/2023 | CAROLEAN BASMA |
| Issued | 9/25/2023 | APPLICANT |
| CofO in Progress | 6/21/2024 | ANTHONY EGSON |
| CofO Issued | 7/9/2024 | DEROLD HAUFF |
| Permit Finaled | 7/9/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/3/2023 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2023 | JESSICA OPINION |
| Sewer availability | Cleared | 7/12/2023 | JESSICA OPINION |
| Low Impact Development (LID) | Cleared | 9/13/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 9/19/2023 | NEIL TUANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Namvar,, Mohammad Alipour; Lic. No.: C39797 | 231 VISTA DEL MAR STE D REDONDO BEACH, CA 90277 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/7/2023 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 11/17/2023 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 11/29/2023 | Approved | ANTHONY EGSON |
| Reinforced Concrete Frame | 11/29/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 12/11/2023 | Partial Approval | ANTHONY EGSON |
| Insulation | 12/11/2023 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2023 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 12/27/2023 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 12/27/2023 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 1/2/2024 | Approved | ANTHONY EGSON |
| Gas Test | 1/2/2024 | Partial Approval | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/2/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 1/8/2024 | Approved | ANTHONY EGSON |
| HVAC-Rough | 1/8/2024 | Approved | ANTHONY EGSON |
| Insulation | 1/12/2024 | Approved | STUART CHAPMAN |
| Drywall Nailing | 1/24/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/29/2024 | Approved | ANTHONY EGSON |
| Underground Mechanical | 3/20/2024 | Approved | ANTHONY EGSON |
| Underground Mechanical | 3/21/2024 | Partial Approval | ANTHONY EGSON |
| Underground Mechanical | 3/22/2024 | Corrections Issued | ANTHONY EGSON |
| Sewer | 3/29/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 4/5/2024 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 4/15/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 4/17/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 5/17/2024 | Approved | ANTHONY EGSON |
| Final | 5/17/2024 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/17/2024 | Approved | ANTHONY EGSON |
| Green Building Final | 5/17/2024 | Approved | ANTHONY EGSON |
| Green Building Rough | 5/17/2024 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 5/17/2024 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 5/17/2024 | Approved | ANTHONY EGSON |
| Final | 5/28/2024 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 5/28/2024 | SGSOV Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 6/20/2024 | Approved | ANTHONY EGSON |
| Final | 6/20/2024 | OK to Issue CofO | ANTHONY EGSON |
| Service/Power Release | 6/20/2024 | Approved | ANTHONY EGSON |