2719 E PEPPER AVE 90065
Certificate Information: 2719 E PEPPER AVE 90065
- Application / Permit
- 23016-30000-15156
- Plan Check / Job No.
- B23WL01229
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Exterior Alteration to a 2story SFD, scope of work to include: replacement of existing roof due to tree collapse per engineer's calcs. (no change in height or floor area)
- Permit Issued
- Issued on 7/24/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 4/2/2024
Permit Application Status History
| Submitted | 5/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/17/2023 | RICHARD GARCIA |
| Corrections Issued | 5/17/2023 | RICHARD GARCIA |
| Building Plans Picked Up | 5/18/2023 | APPLICANT |
| Applicant returned to address corrections | 5/26/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 7/3/2023 | CRISTINA SALAZAR |
| Plan Check Approved | 7/20/2023 | AUNG SOE |
| Issued | 7/24/2023 | APPLICANT |
| Permit Finaled | 4/1/2024 | OSVALDO PARAMO |
Permit Application Clearance Information
| ZI | Cleared | 6/23/2023 | DANIEL CORONADO |
| Supp. Use District POD/CDO/TDO | Cleared | 6/28/2023 | NICOLE SANCHEZ |
Contact Information
| Contractor | Marathon Enterprises Inc; Lic. No.: 1077748-B | 1050 W ALAMEDA AVE #306 BURBANK, CA 91506 |
| Engineer | Morales,, Ricky Augusto; Lic. No.: C40289 | 550 DEEP VALLEY DR STE 273 PALOS VERDES ENGINEERING CORP. ROLLING HILLS ESTATES, CA 90274 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/28/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 9/29/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 9/29/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 10/3/2023 | No Access for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 10/10/2023 | Corrections Issued | AMY COLIN |
| Insulation | 10/12/2023 | Approved | JOSH MEISTER |
| Drywall Nailing | 10/16/2023 | No Access for Inspection | OSVALDO PARAMO |
| Drywall Nailing | 10/17/2023 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 10/17/2023 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 11/27/2023 | Approved | OSVALDO PARAMO |
| Final | 1/2/2024 | Corrections Issued | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 1/2/2024 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 1/2/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 1/23/2024 | Partial Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 1/23/2024 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 1/23/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 2/15/2024 | Corrections Issued | OSVALDO PARAMO |
| Smoke Detectors | 2/15/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 4/1/2024 | Permit Finaled | OSVALDO PARAMO |
| Smoke Detectors | 4/1/2024 | Approved | OSVALDO PARAMO |