1075 N WESTERN AVE 90029
Certificate Information: 1075 N WESTERN AVE 90029
- Application / Permit
- 23016-30000-13392
- Plan Check / Job No.
- B23WL01102
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Office
- Work Description
- Interior / exterior tenant improvement (T.I.) to (e) medical office. Work includes new partitions, finishes, flooring, restrooms, reflected ceiling, furniture, and replace storefront.
- Permit Issued
- Issued on 12/5/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 6/24/2024
Permit Application Status History
| Submitted | 4/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | REZA HAGHIGHAT |
| Corrections Issued | 5/11/2023 | REZA HAGHIGHAT |
| Quality Review Completed | 5/18/2023 | KAVIAN REFAHI |
| Disabled Access Plans Picked Up | 5/23/2023 | APPLICANT |
| Green Plans Picked Up | 5/23/2023 | APPLICANT |
| Plan Check Approved | 11/30/2023 | REZA HAGHIGHAT |
| Issued | 12/5/2023 | APPLICANT |
| Permit Finaled | 6/24/2024 | RONALD JIMENEZ |
Permit Application Clearance Information
| ZA Case | Cleared | 5/24/2023 | RUBEN VASQUEZ |
| ZA Case | Cleared | 5/24/2023 | RUBEN VASQUEZ |
| Green Code | Cleared | 6/20/2023 | MICHAEL AYERS |
| DAS Clearance | Cleared | 8/3/2023 | SHINE LIN |
Contact Information
| Architect | Robidoux,, Douglas Eric; Lic. No.: C30757 | LITTLE 1300 DOVE ST. STE. 100 NEWPORT BEACH, CA 92660 |
| Contractor | Phoenix Construction And Management Inc; Lic. No.: 815136-B | 515 S FLOWER STREET, STE 1270 LOS ANGELES, CA 90071 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/21/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Drilled-In Anchors | 12/26/2023 | Conditional Approval | RAMAZANALI ALMASI |
| Excavation/Setback/Form/Re-Bar | 12/26/2023 | Partial Approval | RAMAZANALI ALMASI |
| Excavation/Setback/Form/Re-Bar | 1/17/2024 | Not Ready for Inspection | RICARDO ROBLES |
| Excavation/Setback/Form/Re-Bar | 1/22/2024 | Corrections Issued | KATY RAMIREZ |
| Deputy Drilled-In Anchors | 1/23/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Light Gage Steel Frame | 1/29/2024 | Corrections Issued | RAMAZANALI ALMASI |
| Light Gage Steel Frame | 2/8/2024 | Partial Inspection | RONALD JIMENEZ |
| Insulation | 2/16/2024 | Approved | RAFAEL CORTES |
| Light Gage Steel Frame | 2/16/2024 | Approved | RAFAEL CORTES |
| Insulation | 2/20/2024 | Approved | RAFAEL CORTES |
| Light Gage Steel Frame | 2/20/2024 | Approved | RAFAEL CORTES |
| Drywall Nailing | 2/22/2024 | Corrections Issued | RAFAEL CORTES |
| Drywall Nailing | 2/23/2024 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 2/26/2024 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 3/27/2024 | Corrections Issued | RAFAEL CORTES |
| T-Bar Ceiling | 4/1/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| T-Bar Ceiling | 4/2/2024 | Not Ready for Inspection | RAFAEL CORTES |
| T-Bar Ceiling | 4/3/2024 | Not Ready for Inspection | RAFAEL CORTES |
| T-Bar Ceiling | 4/4/2024 | Partial Approval | RAFAEL CORTES |
| T-Bar Ceiling | 4/8/2024 | Not Ready for Inspection | RAFAEL CORTES |
| T-Bar Ceiling | 4/9/2024 | Not Ready for Inspection | RAFAEL CORTES |
| T-Bar Ceiling | 4/16/2024 | Partial Approval | RAFAEL CORTES |
| Smoke Detectors | 4/22/2024 | Not Ready for Inspection | RAFAEL CORTES |
| T-Bar Ceiling | 4/22/2024 | No Access for Inspection | RAFAEL CORTES |
| Special/Order Compliance | 5/22/2024 | Approved | RAFAEL CORTES |
| Final | 5/29/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Green Building Final | 5/29/2024 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 5/29/2024 | SGSOV Not Ready | RONALD JIMENEZ |
| Smoke Detectors | 5/29/2024 | Approved | RONALD JIMENEZ |
| Final | 5/31/2024 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 5/31/2024 | SGSOV Not Ready | RAFAEL CORTES |
| Final | 6/4/2024 | Corrections Issued | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 6/4/2024 | SGSOV Not Ready | RAFAEL CORTES |
| Special/Order Compliance | 6/5/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 6/14/2024 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 6/14/2024 | SGSOV No Gas | RAFAEL CORTES |
| Special/Order Compliance | 6/17/2024 | No Access for Inspection | RAFAEL CORTES |
| Final | 6/24/2024 | Permit Finaled | RONALD JIMENEZ |