1515 S PURDUE AVE 1-20 90025

Certificate Information: 1515 S PURDUE AVE 1-20 90025

Application / Permit
23016-30000-13251
Plan Check / Job No.
B23WL01084
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Convert two (E) recreation rooms & lanudry and storage rooms into 4 accessory dwelling units in the basement of an (E) apparment building per CA G.C.S. 65852.2(e)(1)(C).
Permit Issued
Issued on 12/14/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/26/2023 APPLICANT
Assigned to Plan Check Engineer 4/27/2023 JAHANSHAH POURHASSAN
Corrections Issued 5/1/2023 JAHANSHAH POURHASSAN
Quality Review Completed 5/11/2023 KAVIAN REFAHI
Building Plans Picked Up 5/16/2023 APPLICANT
Disabled Access Plans Picked Up 10/18/2023 APPLICANT
Applicant returned to address corrections 11/16/2023 JAHANSHAH POURHASSAN
Applicant returned to address corrections 11/28/2023 JAHANSHAH POURHASSAN
Plan Check Approved 12/1/2023 JAHANSHAH POURHASSAN
Issued 12/14/2023 APPLICANT
CofO in Progress 6/9/2026 CASIMIR BRITTON
Permit Finaled 6/9/2026 VASIL MIHALEV
CofO Issued 6/9/2026 VASIL MIHALEV
Permit Finaled 6/9/2026 VASIL MIHALEV

Permit Application Clearance Information

Address approval Cleared 8/14/2023 JASON NG
Sewer availability Cleared 8/14/2023 JASON NG
Eng Process Fee Ord 176,300 Cleared 8/15/2023 JASON NG
Tenant Habitability Plan Cleared 9/25/2023 RICARDO BOHORQUEZ
DAS Clearance Cleared 11/7/2023 KAVIAN REFAHI
Green Code Cleared 11/7/2023 MICHAEL AYERS
"Q" conditions Cleared 11/15/2023 DAVID URITA

Contact Information

Contractor Owner-Builder       ,
Engineer Cohanzad,, Isaac Wise; Lic. No.: C39474 11601 SANTA MONICA BLVD      LOS ANGELES, CA 90025

Inspector Information

CASIMIR BRITTON, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI
SHAVONNE ESPINOZA, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/22/2024 Approved CASIMIR BRITTON
Green Building Final 10/18/2024 Not Ready for Inspection CASIMIR BRITTON
METHANE-Final 10/18/2024 Not Ready for Inspection CASIMIR BRITTON
Pre-Inspection 10/18/2024 Corrections Issued CASIMIR BRITTON
Green Building Rough 10/25/2024 Not Ready for Inspection CASIMIR BRITTON
METHANE-Rough 10/25/2024 Not Ready for Inspection CASIMIR BRITTON
Wood Frame 10/25/2024 Not Ready for Inspection CASIMIR BRITTON
Insulation 10/31/2024 Partial Approval CASIMIR BRITTON
Drywall Nailing 11/18/2024 Partial Approval CASIMIR BRITTON
Interior/Exterior Lathing 11/22/2024 Partial Approval CASIMIR BRITTON
Footing/Foundation/Slab 2/18/2025 Corrections Issued DANIEL VARNUM
Green Building Rough 3/12/2025 Not Ready for Inspection CASIMIR BRITTON
METHANE-Rough 3/12/2025 Not Ready for Inspection CASIMIR BRITTON
Wood Frame 3/12/2025 Not Ready for Inspection CASIMIR BRITTON
Green Building Rough 4/1/2025 Not Ready for Inspection CASIMIR BRITTON
METHANE-Rough 4/1/2025 Not Ready for Inspection CASIMIR BRITTON
Wood Frame 4/1/2025 Not Ready for Inspection CASIMIR BRITTON
Green Building Rough 4/9/2025 Approved CASIMIR BRITTON
METHANE-Rough 4/9/2025 Approved CASIMIR BRITTON
Wood Frame 4/9/2025 Conditional Approval CASIMIR BRITTON
Insulation 4/10/2025 Approved CASIMIR BRITTON
Drywall Nailing 4/25/2025 Not Ready for Inspection CASIMIR BRITTON
Green Building Final 4/28/2026 No Access for Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 4/28/2026 SGSOV Not Ready DANIEL VARNUM
Smoke Detectors 4/28/2026 No Access for Inspection DANIEL VARNUM
Wood Frame 4/28/2026 No Access for Inspection DANIEL VARNUM
Final 4/30/2026 Corrections Issued CASIMIR BRITTON
Final 5/12/2026 Not Ready for Inspection CASIMIR BRITTON
Green Building Final 5/12/2026 Approved CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 5/12/2026 SGSOV Approved CASIMIR BRITTON
Smoke Detectors 5/12/2026 Approved CASIMIR BRITTON
Wood Frame 5/12/2026 Approved CASIMIR BRITTON
Final 6/3/2026 Not Ready for Inspection CASIMIR BRITTON
Final 6/9/2026 OK to Issue CofO CASIMIR BRITTON