1766 N PALISADES DR 90272
Certificate Information: 1766 N PALISADES DR 90272
- Application / Permit
- 23016-30000-12252
- Plan Check / Job No.
- B23WL01034
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Multi Family
- Work Description
- Remodel an existing bathroom & install new shower in (E) crawl space to add new floor area
- Permit Issued
- Issued on 10/12/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2023 | RICHARD GARCIA |
| Corrections Issued | 4/28/2023 | RICHARD GARCIA |
| Building Plans Picked Up | 5/1/2023 | APPLICANT |
| Applicant returned to address corrections | 8/10/2023 | JOHNPAUL ISIP |
| Plan Check Approved | 10/6/2023 | CAROLEAN BASMA |
| Issued | 10/12/2023 | APPLICANT |
| CofO in Progress | 12/18/2023 | CASIMIR BRITTON |
| CofO in Progress | 12/18/2023 | CASIMIR BRITTON |
| Permit Finaled | 12/18/2023 | DAVID TSAU |
| CofO Issued | 12/18/2023 | DAVID TSAU |
| Permit Finaled | 12/18/2023 | DAVID TSAU |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/16/2023 | VASIL MIHALEV |
| Coastal Zone | Cleared | 9/21/2023 | MAXFIELD VERMY |
| ZA Case | Cleared | 9/21/2023 | MAXFIELD VERMY |
| ZA Case | Cleared | 9/21/2023 | MAXFIELD VERMY |
| ZA Case | Cleared | 9/21/2023 | MAXFIELD VERMY |
| ZA Case | Cleared | 9/21/2023 | MAXFIELD VERMY |
| ZA Case | Cleared | 9/21/2023 | MAXFIELD VERMY |
| Tenant Habitability Plan | Cleared | 10/5/2023 | HUGO GARRIDO GARZA |
Contact Information
| Contractor | Borgese Rocco Pasquale; Lic. No.: 852378-B | 739 10TH STREET, UNIT B SANTA MONICA, CA 90402 |
| Engineer | Guivatchian,, Mohammad; Lic. No.: C36510 | 4720 DEGOVIA AVENUE WOODLAND HILLS, CA 91364 |
Inspector Information
| CASIMIR BRITTON, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAVONNE ESPINOZA, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 10/18/2023 | Approved | ALAN NOVAK |
| Final | 10/18/2023 | Not Ready for Inspection | ALAN NOVAK |
| Green Building Rough | 10/18/2023 | Approved | ALAN NOVAK |
| FLOOD-Proofing Certificate | 11/7/2023 | Approved | CASIMIR BRITTON |
| Final | 11/7/2023 | Not Ready for Inspection | CASIMIR BRITTON |
| SGSOV-Seismic Gas S/O Valve | 11/7/2023 | SGSOV Approved | CASIMIR BRITTON |
| Smoke Detectors | 11/7/2023 | Approved | CASIMIR BRITTON |
| Final | 12/18/2023 | OK to Issue CofO | CASIMIR BRITTON |
| Footing/Foundation/Slab | 12/18/2023 | Approved | CASIMIR BRITTON |
| Green Building Final | 12/18/2023 | Approved | CASIMIR BRITTON |
| Wood Frame | 12/18/2023 | Approved | CASIMIR BRITTON |