617-619 E 85TH ST 90001

Certificate Information: 617-619 E 85TH ST 90001

Application / Permit
23016-30000-11273
Plan Check / Job No.
B23WL00962
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) attached storage conversion to an ADU per CA Govt. Code 65852.2(e)(1)(A). Design per licensed engineer.
Permit Issued
Issued on 11/22/2024
Issuing Office
Metro
Current Status
Issued on 11/22/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/12/2023 APPLICANT
Assigned to Plan Check Engineer 4/20/2023 RICHARD GARCIA
Corrections Issued 4/20/2023 RICHARD GARCIA
Building Plans Picked Up 4/24/2023 APPLICANT
Applicant returned to address corrections 5/25/2023 JOHNPAUL ISIP
Applicant returned to address corrections 6/9/2023 AMY GUEVARRA
Plan Check Approved 11/14/2024 CAROLEAN BASMA
Issued 11/22/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/16/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/31/2023 JEANIE LAM
Sewer availability Cleared 5/31/2023 JEANIE LAM

Contact Information

Contractor Rehab Building Co Inc; Lic. No.: 991087-B 17130 VAN BUREN #556      RIVERSIDE, CA 92504
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 2999 OVERLAND AVE STE 103      LOS ANGELES, CA 90064

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 12/16/2024 Approved JOHN QUINTANILLA
HVAC-Rough 12/16/2024 Corrections Issued JOHN QUINTANILLA
PLUMBING-Rough 12/16/2024 Corrections Issued JOHN QUINTANILLA
HVAC-Rough 12/18/2024 Approved JOHN QUINTANILLA
PLUMBING-Rough 12/18/2024 Approved JOHN QUINTANILLA
Insulation 12/24/2024 Corrections Issued JOHN QUINTANILLA
Insulation 1/27/2025 Approved JOHN QUINTANILLA
Wood Frame 1/27/2025 Approved JOHN QUINTANILLA
Drywall Nailing 2/10/2025 Corrections Issued JOHN QUINTANILLA
BUILDING-Rough-Frame 3/25/2025 Approved JOHN QUINTANILLA
Final 3/25/2025 Corrections Issued JOHN QUINTANILLA
Green Building Final 3/25/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Rough 3/25/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 3/25/2025 SGSOV Not Required JOHN QUINTANILLA
Smoke Detectors 3/25/2025 Approved JOHN QUINTANILLA
Final 4/3/2025 Conditional Approval JOHN QUINTANILLA
Green Building Final 4/3/2025 Approved JOHN QUINTANILLA