623 E SANTA CLARA AVE 90291

Certificate Information: 623 E SANTA CLARA AVE 90291

Application / Permit
23016-30000-08442
Plan Check / Job No.
B23WL00756
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert detached garage into ADU with addition per ordinance
Permit Issued
Issued on 1/26/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/22/2023 APPLICANT
Assigned to Plan Check Engineer 3/30/2023 JAHANSHAH POURHASSAN
Corrections Issued 3/30/2023 JAHANSHAH POURHASSAN
Building Plans Picked Up 4/18/2023 APPLICANT
Applicant returned to address corrections 10/12/2023 MINA HABILI
Plan Check Approved 1/18/2024 WEIJIAN HUANG
Issued 1/26/2024 APPLICANT
CofO in Progress 7/19/2024 HERBERT GIRON
Permit Finaled 7/23/2024 DANIEL ORRANTE
CofO Issued 7/23/2024 DANIEL ORRANTE
Permit Finaled 7/23/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/18/2023 JASON NG
Eng Process Fee Ord 176,300 Cleared 5/18/2023 JASON NG
Sewer availability Cleared 5/18/2023 JASON NG
Roof/Waste drainage to street Cleared 10/19/2023 HISASHI KOBAYAKAWA
Coastal Zone Cleared 1/18/2024 YINGSHI HUANG
Specific Plan Cleared 1/18/2024 YINGSHI HUANG

Contact Information

Contractor Zepeda General Building; Lic. No.: 1028796-B 9525 HUNT AVE      SOUTH GATE, CA 90280
Engineer Garcia,, Lionel J; Lic. No.: S4653 24702 NARBONNE AVE      LOMITA, CA 90717
Engineer Shank,, Ken M; Lic. No.: L8271 2566 N FERNANDO RD      LOS ANGELES, CA 90065

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/2/2024 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 4/17/2024 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 4/24/2024 Partial Approval HERBERT GIRON
Excavation/Setback/Form/Re-Bar 5/2/2024 Approved HERBERT GIRON
Footing/Foundation/Slab 5/2/2024 Approved HERBERT GIRON
ELECTRICAL-Rough 5/8/2024 Corrections Issued HERBERT GIRON
HVAC-Rough 5/8/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 5/8/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 5/23/2024 Corrections Issued HERBERT GIRON
HVAC-Rough 5/23/2024 Approved HERBERT GIRON
PLUMBING-Rough 5/23/2024 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 5/31/2024 Partial Approval HERBERT GIRON
ELECTRICAL-Rough 5/31/2024 Approved HERBERT GIRON
Insulation 5/31/2024 Partial Approval HERBERT GIRON
PLUMBING-Rough 5/31/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 6/6/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 6/6/2024 Approved HERBERT GIRON
Green Building Rough 6/6/2024 Approved HERBERT GIRON
Insulation 6/6/2024 Approved HERBERT GIRON
Wood Frame 6/6/2024 Corrections Issued HERBERT GIRON
Drywall Nailing 6/13/2024 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 6/13/2024 Approved HERBERT GIRON
Drywall Nailing 6/18/2024 Approved HERBERT GIRON
Shower Pan 6/18/2024 Approved HERBERT GIRON
ELECTRICAL-Final 7/11/2024 Corrections Issued HERBERT GIRON
HVAC-Final 7/11/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 7/11/2024 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 7/16/2024 Approved STEPHANIE SWANSON
ELECTRICAL-Final 7/16/2024 Approved STEPHANIE SWANSON
Final 7/16/2024 Partial Approval STEPHANIE SWANSON
Gas Test 7/16/2024 Not Ready for Inspection STEPHANIE SWANSON
Green Building Final 7/16/2024 Approved STEPHANIE SWANSON
HVAC-Final 7/16/2024 Approved STEPHANIE SWANSON
PLUMBING-Final 7/16/2024 Not Ready for Inspection STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 7/16/2024 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 7/16/2024 Corrections Issued STEPHANIE SWANSON
Gas Test 7/18/2024 Approved HERBERT GIRON
PLUMBING-Final 7/18/2024 Approved HERBERT GIRON
Smoke Detectors 7/18/2024 Approved HERBERT GIRON
Final 7/19/2024 OK to Issue CofO HERBERT GIRON
Smoke Detectors 7/19/2024 Approved HERBERT GIRON