623 E SANTA CLARA AVE 90291
Certificate Information: 623 E SANTA CLARA AVE 90291
- Application / Permit
- 23016-30000-08442
- Plan Check / Job No.
- B23WL00756
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert detached garage into ADU with addition per ordinance
- Permit Issued
- Issued on 1/26/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2023 | JAHANSHAH POURHASSAN |
| Corrections Issued | 3/30/2023 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 4/18/2023 | APPLICANT |
| Applicant returned to address corrections | 10/12/2023 | MINA HABILI |
| Plan Check Approved | 1/18/2024 | WEIJIAN HUANG |
| Issued | 1/26/2024 | APPLICANT |
| CofO in Progress | 7/19/2024 | HERBERT GIRON |
| Permit Finaled | 7/23/2024 | DANIEL ORRANTE |
| CofO Issued | 7/23/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/23/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/18/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2023 | JASON NG |
| Sewer availability | Cleared | 5/18/2023 | JASON NG |
| Roof/Waste drainage to street | Cleared | 10/19/2023 | HISASHI KOBAYAKAWA |
| Coastal Zone | Cleared | 1/18/2024 | YINGSHI HUANG |
| Specific Plan | Cleared | 1/18/2024 | YINGSHI HUANG |
Contact Information
| Contractor | Zepeda General Building; Lic. No.: 1028796-B | 9525 HUNT AVE SOUTH GATE, CA 90280 |
| Engineer | Garcia,, Lionel J; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
| Engineer | Shank,, Ken M; Lic. No.: L8271 | 2566 N FERNANDO RD LOS ANGELES, CA 90065 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/2/2024 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 4/17/2024 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 4/24/2024 | Partial Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 5/2/2024 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 5/2/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 5/8/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 5/8/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 5/8/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 5/23/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 5/23/2024 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 5/23/2024 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 5/31/2024 | Partial Approval | HERBERT GIRON |
| ELECTRICAL-Rough | 5/31/2024 | Approved | HERBERT GIRON |
| Insulation | 5/31/2024 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 5/31/2024 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 6/6/2024 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2024 | Approved | HERBERT GIRON |
| Green Building Rough | 6/6/2024 | Approved | HERBERT GIRON |
| Insulation | 6/6/2024 | Approved | HERBERT GIRON |
| Wood Frame | 6/6/2024 | Corrections Issued | HERBERT GIRON |
| Drywall Nailing | 6/13/2024 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 6/13/2024 | Approved | HERBERT GIRON |
| Drywall Nailing | 6/18/2024 | Approved | HERBERT GIRON |
| Shower Pan | 6/18/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 7/11/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 7/11/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 7/11/2024 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 7/16/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 7/16/2024 | Approved | STEPHANIE SWANSON |
| Final | 7/16/2024 | Partial Approval | STEPHANIE SWANSON |
| Gas Test | 7/16/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Green Building Final | 7/16/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 7/16/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 7/16/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 7/16/2024 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 7/16/2024 | Corrections Issued | STEPHANIE SWANSON |
| Gas Test | 7/18/2024 | Approved | HERBERT GIRON |
| PLUMBING-Final | 7/18/2024 | Approved | HERBERT GIRON |
| Smoke Detectors | 7/18/2024 | Approved | HERBERT GIRON |
| Final | 7/19/2024 | OK to Issue CofO | HERBERT GIRON |
| Smoke Detectors | 7/19/2024 | Approved | HERBERT GIRON |