408 E LINNIE CL 90291
Certificate Information: 408 E LINNIE CL 90291
- Application / Permit
- 23016-30000-07706
- Plan Check / Job No.
- B23WL00692
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior And Exterior Renovation and Structural Remodel Of (E) Single Family Dwelling
- Permit Issued
- Issued on 11/9/2023
- Issuing Office
- Current Status
- Issued on 11/9/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2023 | RICHARD GARCIA |
| Corrections Issued | 3/16/2023 | RICHARD GARCIA |
| Applicant returned to address corrections | 4/12/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 5/8/2023 | EDWIN ESPIN |
| Plan Check Approved | 10/23/2023 | EDWIN ESPIN |
| Issued | 11/9/2023 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/10/2023 | KENTON TRINH |
| ZI | Cleared | 4/10/2023 | KENTON TRINH |
| Coastal Zone | Cleared | 4/11/2023 | KENTON TRINH |
| HPOZ | Cleared | 4/11/2023 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 4/11/2023 | LAMBERT GIESSINGER |
| City Hist. Cultural Monument | Cleared | 4/24/2023 | LAMBERT GIESSINGER |
| Flood clearance | Cleared | 10/11/2023 | TUYEN LE |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2023 | ANTHONY MAINEZ |
| Coastal Zone | Cleared | 10/17/2023 | YINGSHI HUANG |
Contact Information
| Architect | Peters,, Curt Austin; Lic. No.: C30632 | 23177 LA CADENA DRIVE SUITE 101 LAGUNA HILLS, CA 92656 |
| Contractor | De Priest David; Lic. No.: 814310-B | 3768 COUNTRY CLUB DRIVE LONG BEACH, CA 90807 |
| Engineer | Garcia,, Lionel J; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/14/2023 | No Access for Inspection | ANDREW BEELI |
| Pre-Inspection | 11/27/2023 | Corrections Issued | ANDREW BEELI |
| PLUMBING-Rough | 2/2/2024 | Not Ready for Inspection | ANDREW BEELI |
| ELECTRICAL-Rough | 4/18/2024 | Corrections Issued | ANDREW BEELI |
| HVAC-Rough | 4/18/2024 | Corrections Issued | ANDREW BEELI |
| PLUMBING-Rough | 4/18/2024 | Not Ready for Inspection | ANDREW BEELI |
| Wood Frame | 4/18/2024 | Corrections Issued | ANDREW BEELI |
| Footing/Foundation/Slab | 5/3/2024 | Approved | ANDREW BEELI |
| Rough-Elec/Plmb/HVAC | 5/16/2024 | Approved | ANDREW BEELI |
| BUILDING-Rough-Frame | 7/9/2024 | Approved | ANDREW BEELI |
| METHANE-Rough | 7/9/2024 | Approved | ANDREW BEELI |
| Insulation | 7/31/2024 | Approved | ANDREW BEELI |
| Interior/Exterior Lathing | 7/31/2024 | Approved | ANDREW BEELI |
| Shower Pan | 7/31/2024 | Approved | ANDREW BEELI |
| Drywall Nailing | 8/19/2024 | Approved | ANDREW BEELI |
| Final | 6/18/2025 | Corrections Issued | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 6/18/2025 | SGSOV Not Ready | ANDREW BEELI |
| Smoke Detectors | 6/18/2025 | Approved | ANDREW BEELI |
| Final | 9/10/2025 | Corrections Issued | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 9/10/2025 | SGSOV Not Ready | ANDREW BEELI |
| Final | 1/20/2026 | Not Ready for Inspection | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 1/20/2026 | SGSOV Not Ready | ANDREW BEELI |
| Final | 3/12/2026 | Corrections Issued | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 3/12/2026 | SGSOV Not Ready | ANDREW BEELI |
| Final | 3/24/2026 | Partial Approval | ANDREW BEELI |
| Gas Test | 3/24/2026 | Approved | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 3/24/2026 | SGSOV Approved | ANDREW BEELI |
| ELECTRICAL-Final | 3/25/2026 | Approved | ANDREW BEELI |
| Green Building Final | 3/25/2026 | Approved | ANDREW BEELI |
| Green Building Rough | 3/25/2026 | Approved | ANDREW BEELI |
| HVAC-Final | 3/25/2026 | Approved | ANDREW BEELI |
| MERV13>=Final | 3/25/2026 | Approved | ANDREW BEELI |
| PLUMBING-Final | 3/25/2026 | Approved | ANDREW BEELI |