11525 1/2 W NEBRASKA AVE 90025
Certificate Information: 11525 1/2 W NEBRASKA AVE 90025
- Application / Permit
- 23016-30000-07339
- Plan Check / Job No.
- B23WL00653
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Covert (E) detatached Garage to an Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A). All work per engineered plans.
- Permit Issued
- Issued on 7/18/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2023 | RICHARD GARCIA |
| Corrections Issued | 3/21/2023 | RICHARD GARCIA |
| Building Plans Picked Up | 3/23/2023 | APPLICANT |
| Applicant returned to address corrections | 4/18/2023 | VICTOR CHEN |
| Applicant returned to address corrections | 5/17/2023 | DANIEL SMILEY |
| Applicant returned to address corrections | 6/9/2023 | MICHAEL LANZONE |
| Issued | 7/18/2023 | APPLICANT |
| CofO in Progress | 2/7/2025 | KIRK SANDERS |
| Permit Finaled | 2/11/2025 | RICHARD STEINBACH |
| CofO Issued | 2/11/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/11/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 5/11/2023 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 5/11/2023 | DARIN LAM |
| Sewer availability | Cleared | 5/11/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2023 | DARIN LAM |
| "Q" conditions | Cleared | 6/9/2023 | DANIEL CORONADO |
| Specific Plan | Cleared | 6/20/2023 | FREDDY GARCIA |
Contact Information
| Contractor | Nunez General Contractors Inc; Lic. No.: 912178-B | P O BOX 1079 SOUTH GATE, CA 90280 |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/9/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 9/9/2024 | Partial Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 9/20/2024 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 9/20/2024 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 10/28/2024 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 10/28/2024 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2024 | Partial Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 10/28/2024 | Conditional Approval | KIRK SANDERS |
| Green Building Rough | 10/28/2024 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 10/28/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 10/28/2024 | Approved | KIRK SANDERS |
| Special/Order Compliance | 10/28/2024 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 11/4/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 11/12/2024 | Partial Approval | KIRK SANDERS |
| HVAC-Rough | 11/12/2024 | Partial Approval | KIRK SANDERS |
| Insulation | 11/12/2024 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 11/12/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 11/14/2024 | Approved | BOBBY KEY |
| Green Building Rough | 11/14/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 11/18/2024 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 11/18/2024 | Approved | KIRK SANDERS |
| Shower Pan | 11/18/2024 | Approved | KIRK SANDERS |
| Final | 11/19/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 12/13/2024 | Corrections Issued | KIRK SANDERS |
| Final | 12/13/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 12/13/2024 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Final | 12/13/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 12/13/2024 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/13/2024 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 12/13/2024 | Approved | KIRK SANDERS |
| Final | 12/30/2024 | Corrections Issued | KIRK SANDERS |
| Final | 2/3/2025 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 2/3/2025 | Approved | KIRK SANDERS |
| Final | 2/6/2025 | OK to Issue CofO | KIRK SANDERS |
| Service/Power Release | 2/6/2025 | Approved | KIRK SANDERS |