5404-5406 N NOBLE AVE 91411

Certificate Information: 5404-5406 N NOBLE AVE 91411

Application / Permit
23016-30000-05289
Plan Check / Job No.
B23WL00458
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (e) 2-car garage into an ADU PER GCS 65852.2(e)(1)(A) and per Engineer's design and details.
Permit Issued
Issued on 6/9/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2023 APPLICANT
Assigned to Plan Check Engineer 3/4/2023 RICHARD GARCIA
Corrections Issued 3/4/2023 RICHARD GARCIA
Building Plans Picked Up 3/7/2023 APPLICANT
Applicant returned to address corrections 3/22/2023 RICHARD GARCIA
Plan Check Approved 3/24/2023 DAVID CASTILLO
Issued 6/9/2023 APPLICANT
CofO in Progress 4/16/2024 THOMAS FINNILA
Permit Finaled 5/1/2024 RUBEN SALAS
CofO Issued 5/1/2024 RUBEN SALAS
Permit Finaled 5/1/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/14/2023 MEGAN GODINEZ
Sewer availability Cleared 3/14/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 3/21/2023 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/15/2023 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 11/17/2023 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 11/22/2023 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 12/7/2023 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 12/7/2023 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 12/8/2023 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 12/8/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 12/8/2023 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 12/12/2023 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 12/12/2023 Conditional Approval THOMAS FINNILA
Green Building Rough 12/12/2023 Approved THOMAS FINNILA
HVAC-Rough 12/12/2023 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 12/12/2023 Partial Approval THOMAS FINNILA
PLUMBING-Rough 12/12/2023 Approved THOMAS FINNILA
Drywall Nailing 12/15/2023 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 12/15/2023 Approved THOMAS FINNILA
Insulation 12/15/2023 Approved THOMAS FINNILA
Drywall Nailing 12/19/2023 Approved THOMAS FINNILA
Shower Pan 12/19/2023 Approved THOMAS FINNILA
ELECTRICAL-Final 2/29/2024 Not Ready for Inspection THOMAS FINNILA
Final 2/29/2024 Corrections Issued THOMAS FINNILA
PLUMBING-Final 2/29/2024 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 2/29/2024 SGSOV Not Ready THOMAS FINNILA
BUILDING-Rough-Frame 4/1/2024 Approved THOMAS FINNILA
Final 4/1/2024 OK to Issue CofO THOMAS FINNILA
Green Building Final 4/1/2024 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 4/1/2024 SGSOV Approved THOMAS FINNILA
Service/Power Release 4/1/2024 Approved THOMAS FINNILA
Smoke Detectors 4/1/2024 Approved THOMAS FINNILA