- Permit Issued
- Issued on 10/3/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2023 | RICHARD GARCIA |
| Corrections Issued | 2/24/2023 | RICHARD GARCIA |
| Building Plans Picked Up | 2/28/2023 | APPLICANT |
| Applicant returned to address corrections | 3/9/2023 | JASON JANGADA |
| Applicant returned to address corrections | 7/18/2023 | CAROLEAN BASMA |
| Plan Check Approved | 7/24/2023 | JAHANSHAH POURHASSAN |
| Issued | 10/3/2023 | APPLICANT |
| CofO in Progress | 9/10/2024 | ARAM AVEDISIAN |
| Permit Finaled | 9/17/2024 | RICHARD STEINBACH |
| CofO Issued | 9/17/2024 | RICHARD STEINBACH |
| Permit Finaled | 9/17/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 3/1/2023 | JEANIE LAM |
| Sewer availability | Cleared | 3/1/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2023 | JEANIE LAM |
| Construction near power lines | Cleared | 6/8/2023 | RIDWAN HARDY |
| Tenant Habitability Plan | Cleared | 6/16/2023 | RICARDO BOHORQUEZ |
| CPC | Cleared | 6/21/2023 | YINGSHI HUANG |
Contact Information
| Contractor | Smart Eye Construction Corp; Lic. No.: 1077004-B | 4059 W 106TH ST INGLEWOOD, CA 90304 |
| Engineer | Perazzelli,, Joseph Ames; Lic. No.: C35270 | 183 GREENFIELD AVENUE LOS ANGELES, CA 90049 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/16/2023 | Approved | MEL KHACHATOURIAN |
| Pre-Inspection | 10/23/2023 | Partial Inspection | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 10/30/2023 | Corrections Issued | MICHAEL PELHAM |
| Pre-Inspection | 11/22/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Pre-Inspection | 11/30/2023 | Approved | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 12/6/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 12/8/2023 | Approved | MEL KHACHATOURIAN |
| Wood Frame | 3/4/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2024 | Partial Approval | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 3/6/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| METHANE-Rough | 3/6/2024 | Approved | MEL KHACHATOURIAN |
| Deputy Drilled-In Anchors | 4/5/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 4/5/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Pre-Inspection | 4/5/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 5/9/2024 | Partial Approval | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 5/10/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 5/23/2024 | Corrections Issued | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 5/23/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Rough | 5/23/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 5/23/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Underground Mechanical | 5/23/2024 | Partial Approval | MEL KHACHATOURIAN |
| Wood Frame | 5/23/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 5/29/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 5/29/2024 | Partial Approval | MEL KHACHATOURIAN |
| HVAC-Rough | 5/29/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 5/29/2024 | Approved | MEL KHACHATOURIAN |
| Underground Mechanical | 5/29/2024 | Approved | MEL KHACHATOURIAN |
| Insulation | 6/3/2024 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 6/5/2024 | Approved | MEL KHACHATOURIAN |
| Drywall Nailing | 6/6/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 6/21/2024 | Partial Approval | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 6/21/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 7/2/2024 | Approved | MEL KHACHATOURIAN |
| Service/Power Release | 7/2/2024 | Approved | MEL KHACHATOURIAN |
| Final | 8/19/2024 | Partial Inspection | DAVID FEILER |
| HVAC-Final | 8/19/2024 | Corrections Issued | DAVID FEILER |
| PLUMBING-Final | 8/19/2024 | Corrections Issued | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 8/19/2024 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 8/19/2024 | Corrections Issued | DAVID FEILER |
| Final | 8/23/2024 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Final | 8/23/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| PLUMBING-Final | 8/23/2024 | Corrections Issued | STEPHANIE SWANSON |
| Smoke Detectors | 8/23/2024 | Approved | STEPHANIE SWANSON |
| Final | 9/10/2024 | OK to Issue CofO | ARAM AVEDISIAN |
| HVAC-Final | 9/10/2024 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 9/10/2024 | Approved | ARAM AVEDISIAN |