10769 W OHIO AVE 1-4 90024
Certificate Information: 10769 W OHIO AVE 1-4 90024
- Application / Permit
- 23016-30000-02715
- Plan Check / Job No.
- B23WL00260
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Interior non-structural remodel. Change of use of (e) management office into an ADU
- Permit Issued
- Issued on 3/7/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/9/2023 | RICHARD GARCIA |
| Corrections Issued | 2/9/2023 | RICHARD GARCIA |
| Building Plans Picked Up | 2/13/2023 | APPLICANT |
| Applicant returned to address corrections | 2/27/2023 | AMY GUEVARRA |
| Plan Check Approved | 3/7/2023 | AMY GUEVARRA |
| Issued | 3/7/2023 | APPLICANT |
| CofO in Progress | 3/29/2023 | PAUL DAVIDSON |
| CofO in Progress | 3/29/2023 | PAUL DAVIDSON |
| Permit Finaled | 3/31/2023 | DAVID TSAU |
| CofO Issued | 3/31/2023 | DAVID TSAU |
| Permit Finaled | 3/31/2023 | DAVID TSAU |
Permit Application Clearance Information
| Address approval | Cleared | 2/16/2023 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2023 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 2/16/2023 | ANTHONY MAINEZ |
| "Q" conditions | Cleared | 2/22/2023 | MAYELA VILLA |
| Specific Plan | Cleared | 3/2/2023 | ALESSANDRO MERCURI |
| Specific Plan | Cleared | 3/3/2023 | KEVIN FULTON |
Contact Information
| Contractor | Eurocon Group Inc; Lic. No.: 708010-B | 923 HILTS AVE LOS ANGELES, CA 90024 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Final | 3/10/2023 | Approved | PAUL DAVIDSON |
| METHANE-Rough | 3/10/2023 | Approved | PAUL DAVIDSON |
| Pre-Inspection | 3/10/2023 | Approved | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 3/10/2023 | SGSOV No Gas | PAUL DAVIDSON |
| Smoke Detectors | 3/10/2023 | Approved | PAUL DAVIDSON |
| Wood Frame | 3/10/2023 | Approved | PAUL DAVIDSON |
| Final | 3/24/2023 | OK to Issue CofO | PAUL DAVIDSON |