13631 W VAN NUYS BLVD 91331
Certificate Information: 13631 W VAN NUYS BLVD 91331
- Application / Permit
- 23016-20002-09477
- Plan Check / Job No.
- B24VN09016
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (10) Special Care Home
- Work Description
- SUPPLEMENTAL PERMIT TO 23016-20000-09477 TO REVISE WORK DESCRIPTION TO CHANGE OF USE FROM OFFICE TO DRUG REHABILITATION FACILITY
- Permit Issued
- Issued on 12/4/2024
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 10/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2024 | RAPHAEL ROSAS |
| Corrections Issued | 7/2/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 7/3/2024 | STEVEN KIM |
| Building Plans Picked Up | 7/17/2024 | APPLICANT |
| Plan Check Approved | 12/4/2024 | RAPHAEL ROSAS |
| Issued | 12/4/2024 | APPLICANT |
| Permit Finaled | 10/8/2025 | ANDREW DORSO |
Permit Application Clearance Information
| "Q" conditions | Cleared | 8/1/2024 | NATHAN ROMINE |
| Miscellaneous | Cleared | 8/1/2024 | NATHAN ROMINE |
| Sewer availability | Cleared | 8/2/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 8/2/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2024 | LEE GUILBEAUX |
| Supp. Use District POD/CDO/TDO | Cleared | 8/14/2024 | ERICK MARCHENA |
| ZI | Cleared | 8/14/2024 | ERICK MARCHENA |
| Fire Marshal Fire Life Safety | Cleared | 9/26/2024 | FIRE DEPARTMENT |
| DAS Clearance | Cleared | 11/21/2024 | RAPHAEL ROSAS |
| Hydrant and Access approval | Cleared | 11/22/2024 | KURT CORRAL |
Contact Information
| Contractor | Nork Construction Inc; Lic. No.: 1058592-B | 835 E HARVARD RD BURBANK, CA 91501 |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 1/7/2025 | Approved | ANDREW DORSO |
| Drywall Nailing | 1/14/2025 | Partial Inspection | ANDREW DORSO |
| Interior/Exterior Lathing | 2/19/2025 | Not Ready for Inspection | ANDREW DORSO |
| Interior/Exterior Lathing | 2/21/2025 | Approved | ANDREW DORSO |
| Final | 10/8/2025 | Permit Finaled | ANDREW DORSO |
| METHANE-Final | 10/8/2025 | Approved | ANDREW DORSO |
| METHANE-Rough | 10/8/2025 | Approved | ANDREW DORSO |
| Wood Frame | 10/8/2025 | Approved | ANDREW DORSO |