8407 N FALLBROOK AVE 91304
Certificate Information: 8407 N FALLBROOK AVE 91304
- Application / Permit
- 23016-20001-19837
- Plan Check / Job No.
- B23VN13981
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Storage Building
- Work Description
- ePLAN****PROPOSED EQUIPMENT ENCLOSURE
- Permit Issued
- Issued on 5/21/2024
- Issuing Office
- Current Status
- Permit Finaled on 11/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2023 | SINA KHOSRAVI |
| Corrections Issued | 11/9/2023 | SINA KHOSRAVI |
| Quality Review Completed | 11/16/2023 | QUAN NGHIEM |
| Applicant returned to address corrections | 1/22/2024 | SINA KHOSRAVI |
| Applicant returned to address corrections | 2/14/2024 | SINA KHOSRAVI |
| Plan Check Approved | 5/15/2024 | SINA KHOSRAVI |
| Issued | 5/21/2024 | APPLICANT |
| Permit Finaled-Status Void | 11/6/2024 | DEANDRE HOFFMAN |
| Re-Activate Permit | 11/6/2024 | DEANDRE HOFFMAN |
| Permit Finaled | 11/20/2024 | DEANDRE HOFFMAN |
Permit Application Clearance Information
| Address approval | Cleared | 11/14/2023 | BRYAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 11/14/2023 | BRYAN GODINEZ |
| Sewer availability | Cleared | 11/14/2023 | BRYAN GODINEZ |
| "Q" conditions | Cleared | 11/15/2023 | DANIEL CORONADO |
| "T" removal | Cleared | 11/15/2023 | DANIEL CORONADO |
| ZA Case | Cleared | 11/15/2023 | DANIEL CORONADO |
| ZI | Cleared | 11/15/2023 | DANIEL CORONADO |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2023 | BRYAN GODINEZ |
| DAS Clearance | Cleared | 1/8/2024 | Gurunath Nesarajah |
| Green Code | Cleared | 1/9/2024 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 1/19/2024 | GILBERT URREA |
| Fire Marshal Fire Life Safety | Cleared | 3/5/2024 | FIRE DEPARTMENT |
| GPI Written Notices | Cleared | 5/15/2024 | SINA KHOSRAVI |
| Grading Pre-Inspection | Cleared | 5/15/2024 | SINA KHOSRAVI |
Contact Information
| Architect | Dwyer,, Susan M; Lic. No.: NA33724 | , |
| Contractor | Howard Building Corporation; Lic. No.: 445804-B | , |
| Engineer | Bishoff,, Ryam William; Lic. No.: S6250 | 9252 DALTON CIRCLE WESTMINSTER, CA 92683 |
Inspector Information
| GREGORY POMISH, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDWIN GREGORYONA, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/17/2024 | Conditional Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 6/21/2024 | Partial Approval | DEANDRE HOFFMAN |
| Masonry Wall/Backfill | 7/5/2024 | Corrections Issued | ROBERT DAVIS |
| Masonry Wall/Backfill | 7/9/2024 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 7/10/2024 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Masonry | 7/10/2024 | Conditional Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 7/10/2024 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 7/11/2024 | Conditional Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 7/16/2024 | Partial Approval | GREGORY POMISH |
| Masonry Wall/Backfill | 7/22/2024 | Partial Inspection | DEANDRE HOFFMAN |
| Masonry Wall/Backfill | 7/23/2024 | Partial Approval | DEANDRE HOFFMAN |
| Deputy Reinf. Masonry | 7/24/2024 | Conditional Approval | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 8/9/2024 | Approved | DEANDRE HOFFMAN |
| Deputy Steel/Welding | 8/16/2024 | Conditional Approval | CAMERON CHABAN |
| Light Gage Steel Frame | 8/23/2024 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 8/28/2024 | Approved | DEANDRE HOFFMAN |
| Final | 11/18/2024 | Not Ready for Inspection | BRIAN KELLY |
| Footing/Foundation/Slab | 11/18/2024 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Final | 11/18/2024 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Rough | 11/18/2024 | Not Ready for Inspection | BRIAN KELLY |
| Reinforced Concrete Frame | 11/18/2024 | Not Ready for Inspection | BRIAN KELLY |
| Smoke Detectors | 11/18/2024 | Not Ready for Inspection | BRIAN KELLY |
| Verify Sprinkler Sign Off | 11/18/2024 | Not Ready for Inspection | BRIAN KELLY |
| Final | 11/20/2024 | Permit Finaled | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 11/20/2024 | Approved | DEANDRE HOFFMAN |
| Green Building Final | 11/20/2024 | Approved | DEANDRE HOFFMAN |
| Green Building Rough | 11/20/2024 | Approved | DEANDRE HOFFMAN |
| Reinforced Concrete Frame | 11/20/2024 | Approved | DEANDRE HOFFMAN |
| Smoke Detectors | 11/20/2024 | Approved | DEANDRE HOFFMAN |
| Verify Sprinkler Sign Off | 11/20/2024 | Approved | DEANDRE HOFFMAN |