6911-6913 N VANALDEN AVE 91335

Certificate Information: 6911-6913 N VANALDEN AVE 91335

Application / Permit
23016-20000-45469
Plan Check / Job No.
B23VN17910
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
convert existing attached garage into JADU in existing one story sfd per engineer design (Junior ADU per State Law, CA Govt. Code 65852.2(e)(1)(A) and 65852.22)
Permit Issued
Issued on 6/19/2024
Issuing Office
Current Status
CofO Issued on 4/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/7/2024 APPLICANT
Assigned to Plan Check Engineer 2/9/2024 AUNG SOE
Corrections Issued 2/12/2024 AUNG SOE
Applicant returned to address corrections 3/15/2024 AUNG SOE
Applicant returned to address corrections 5/15/2024 DANIEL SMILEY
Applicant returned to address corrections 6/14/2024 AUNG SOE
Plan Check Approved 6/18/2024 CARLOS MONTES
Issued 6/19/2024 APPLICANT
CofO in Progress 4/17/2026 ARUTYUN MADATYAN
Permit Finaled 4/30/2026 JOHN JANSON
CofO Issued 4/30/2026 JOHN JANSON
Permit Finaled 4/30/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/12/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/12/2024 LEE GUILBEAUX
Sewer availability Cleared 3/12/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/12/2024 LEE GUILBEAUX
ZI Cleared 4/2/2024 RUBEN VASQUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Seckler,, Wiliam` Stewart; Lic. No.: C24044 3935 LA SIERRA AVE 99      RIVERSIDE, CA 92505

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/20/2024 Not Ready for Inspection DAVID SCANTLIN
Footing/Foundation/Slab 11/26/2024 Not Ready for Inspection ARUTYUN MADATYAN
Deputy Drilled-In Anchors 11/27/2024 Approved ARUTYUN MADATYAN
Footing/Foundation/Slab 12/2/2024 No Access for Inspection ARUTYUN MADATYAN
Sewer 12/2/2024 No Access for Inspection ARUTYUN MADATYAN
Footing/Foundation/Slab 12/6/2024 Approved ARUTYUN MADATYAN
PLUMBING-Rough 12/6/2024 Partial Approval ARUTYUN MADATYAN
Sewer 12/6/2024 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 1/17/2025 Corrections Issued ARUTYUN MADATYAN
Deputy Drilled-In Anchors 1/17/2025 Conditional Approval ARUTYUN MADATYAN
Green Building Rough 1/17/2025 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 5/16/2025 Corrections Issued JUAN ALVARADO
Green Building Rough 5/16/2025 Not Ready for Inspection JUAN ALVARADO
Wood Frame 5/16/2025 Not Ready for Inspection JUAN ALVARADO
Deputy Drilled-In Anchors 5/22/2025 Conditional Approval ARUTYUN MADATYAN
Deputy Drilled-In Anchors 5/27/2025 Conditional Approval ARUTYUN MADATYAN
Wood Frame 6/9/2025 Not Ready for Inspection ARUTYUN MADATYAN
Pre-Inspection 6/17/2025 Partial Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 7/7/2025 Approved KRISTEN CAUSEY
PLUMBING-Rough 7/7/2025 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 7/28/2025 Corrections Issued ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 7/28/2025 Corrections Issued ARUTYUN MADATYAN
Insulation 7/28/2025 Not Ready for Inspection ARUTYUN MADATYAN
Interior/Exterior Lathing 7/29/2025 No Access for Inspection ARUTYUN MADATYAN
Insulation 8/19/2025 Partial Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 8/27/2025 Partial Approval ARUTYUN MADATYAN
Drywall Nailing 9/24/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 11/19/2025 Partial Approval CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 1/16/2026 SGSOV Not Ready ARUTYUN MADATYAN
ELECTRICAL-Final 1/20/2026 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Final 1/20/2026 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Final 1/20/2026 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 1/23/2026 Approved ARUTYUN MADATYAN
Final 1/23/2026 Corrections Issued ARUTYUN MADATYAN
Green Building Final 1/23/2026 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Rough 1/23/2026 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 1/23/2026 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 1/23/2026 Not Ready for Inspection ARUTYUN MADATYAN
Final 1/30/2026 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Final 4/16/2026 Approved ARUTYUN MADATYAN
Final 4/16/2026 OK to Issue CofO ARUTYUN MADATYAN
Green Building Final 4/16/2026 Approved ARUTYUN MADATYAN
HVAC-Final 4/16/2026 Approved ARUTYUN MADATYAN
PLUMBING-Final 4/16/2026 Approved ARUTYUN MADATYAN
Smoke Detectors 4/16/2026 Approved ARUTYUN MADATYAN