22948-22950 W LULL ST 91304
Certificate Information: 22948-22950 W LULL ST 91304
- Application / Permit
- 23016-20000-45383
- Plan Check / Job No.
- B23VN17864
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Convert (E) attached Garage into ADU per CA Govt. Code 65852.2(e)(1)(A) . Work per Wood Frame Prescriptive Provisions .
- Permit Issued
- Issued on 9/2/2025
- Issuing Office
- Current Status
- CofO Issued on 5/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2024 | MINA HABILI |
| Corrections Issued | 1/5/2024 | MINA HABILI |
| Applicant returned to address corrections | 2/21/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 4/26/2024 | MINA HABILI |
| Plan Check Approved | 5/7/2024 | GEORGE ALVAREZ |
| Issued | 9/2/2025 | APPLICANT |
| CofO in Progress | 5/18/2026 | CHRIS CHRISTENSEN |
| Permit Finaled | 5/20/2026 | JOHN JANSON |
| CofO Issued | 5/20/2026 | JOHN JANSON |
| Permit Finaled | 5/20/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/16/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/16/2024 | EDGAR ALCARAZ |
| ZA Case | Cleared | 1/16/2024 | STEVEN WECHSLER |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/4/2025 | Approved | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 11/6/2025 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 11/7/2025 | Approved | HENRY KIM |
| PLUMBING-Rough | 11/18/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Sewer | 11/18/2025 | Approved | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 12/9/2025 | Conditional Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/12/2025 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 12/12/2025 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 12/12/2025 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 12/12/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 12/15/2025 | Conditional Approval | JEFFREY HARTLINE |
| Wood Frame | 12/19/2025 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 12/26/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 12/29/2025 | Partial Approval | KRISTEN CAUSEY |
| Insulation | 12/31/2025 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 12/31/2025 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 1/5/2026 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 1/5/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 1/9/2026 | Partial Approval | CHRIS CHRISTENSEN |
| Shower Pan | 1/9/2026 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 2/19/2026 | Approved | CHRIS CHRISTENSEN |
| Gas Test | 2/19/2026 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 2/19/2026 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 2/19/2026 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 2/19/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 5/8/2026 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 5/8/2026 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 5/8/2026 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 5/8/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 5/8/2026 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 5/8/2026 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Service/Power Release | 5/8/2026 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 5/8/2026 | Approved | CHRIS CHRISTENSEN |
| Final | 5/15/2026 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 5/15/2026 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 5/15/2026 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 5/15/2026 | Approved | CHRIS CHRISTENSEN |