22053 W VANOWEN ST 91303
Certificate Information: 22053 W VANOWEN ST 91303
- Application / Permit
- 23016-20000-45362
- Plan Check / Job No.
- B23VN17850
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert existing detached garage to ADU per CA Govt. code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 1/17/2024
- Issuing Office
- Current Status
- CofO Issued on 5/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2024 | CAROLEAN BASMA |
| Corrections Issued | 1/3/2024 | CAROLEAN BASMA |
| Plan Check Approved | 1/15/2024 | CAROLEAN BASMA |
| Issued | 1/17/2024 | APPLICANT |
| CofO in Progress | 4/25/2024 | GEVORK IPCHYAN |
| Permit Finaled | 5/6/2024 | JOHN JANSON |
| CofO Issued | 5/6/2024 | JOHN JANSON |
| Permit Finaled | 5/6/2024 | JOHN JANSON |
Permit Application Clearance Information
| ZI | Cleared | 1/4/2024 | STEVEN WECHSLER |
| Address approval | Cleared | 1/5/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/5/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/9/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ebrahimian, Dehaghani, Mahdi; Lic. No.: C86987 | 18543 DEVONSHIRE ST, #202 NORTHRIDGE, CA 91324 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/25/2024 | Approved | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 1/31/2024 | Approved | MORRIS JACKSON |
| Underground Mechanical | 2/9/2024 | Approved | MORRIS JACKSON |
| Underground Mechanical | 2/15/2024 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 2/21/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 2/21/2024 | Approved | GEVORK IPCHYAN |
| Green Building Rough | 2/21/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Underground Mechanical | 2/21/2024 | Approved | GEVORK IPCHYAN |
| PLUMBING-Rough | 2/26/2024 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 3/5/2024 | Approved | GEVORK IPCHYAN |
| HVAC-Rough | 3/5/2024 | Partial Approval | GEVORK IPCHYAN |
| Insulation | 3/12/2024 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 3/12/2024 | Approved | GEVORK IPCHYAN |
| Drywall Nailing | 3/18/2024 | Approved | GEVORK IPCHYAN |
| Green Building Rough | 3/18/2024 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 3/18/2024 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 4/19/2024 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 4/19/2024 | Partial Approval | GEVORK IPCHYAN |
| Final | 4/19/2024 | Partial Approval | GEVORK IPCHYAN |
| Green Building Final | 4/19/2024 | Approved | GEVORK IPCHYAN |
| HVAC-Final | 4/19/2024 | Approved | GEVORK IPCHYAN |
| PLUMBING-Final | 4/19/2024 | Approved | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/19/2024 | SGSOV Approved | GEVORK IPCHYAN |
| Smoke Detectors | 4/19/2024 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 4/24/2024 | Approved | GEVORK IPCHYAN |
| Final | 4/24/2024 | OK to Issue CofO | GEVORK IPCHYAN |
| Service/Power Release | 4/24/2024 | Approved | GEVORK IPCHYAN |