19761 W ROSCOE BLVD 91306

Certificate Information: 19761 W ROSCOE BLVD 91306

Application / Permit
23016-20000-45237
Plan Check / Job No.
B23VN17770
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
* * ePlan * * Dettached Garage at rear of the lot conversion to an ADU per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 1/23/2024
Issuing Office
Current Status
CofO Issued on 2/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2023 APPLICANT
Assigned to Plan Check Engineer 1/3/2024 EDWIN ESPIN
Corrections Issued 1/3/2024 EDWIN ESPIN
Plan Check Approved 1/21/2024 EDWIN ESPIN
Issued 1/23/2024 APPLICANT
CofO in Progress 2/20/2026 JEFFREY HARTLINE
Permit Finaled 2/23/2026 JOHN JANSON
CofO Issued 2/23/2026 JOHN JANSON
Permit Finaled 2/23/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/13/2024 EDGAR ALCARAZ
Sewer availability Cleared 1/13/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/16/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Maalouf,, Sami; Lic. No.: NA53210       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/13/2025 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 3/20/2025 Partial Approval JEFFREY HARTLINE
Footing/Foundation/Slab 3/20/2025 Corrections Issued JEFFREY HARTLINE
Deputy Drilled-In Anchors 4/1/2025 Conditional Approval SCOTT SOBEL
Floor/Roof Diaphrgm/Shear Wall 5/8/2025 No Access for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 10/22/2025 Not Ready for Inspection JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 10/22/2025 Partial Approval JEFFREY HARTLINE
Wood Frame 10/22/2025 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 12/24/2025 Approved JEFFREY HARTLINE
Insulation 12/24/2025 Not Ready for Inspection JEFFREY HARTLINE
Underground Mechanical 12/24/2025 Not Ready for Inspection JEFFREY HARTLINE
BUILDING-Rough-Frame 12/26/2025 Approved JEFFREY HARTLINE
Green Building Rough 12/26/2025 Approved JEFFREY HARTLINE
HVAC-Rough 12/26/2025 Approved JEFFREY HARTLINE
Insulation 12/26/2025 Approved JEFFREY HARTLINE
PLUMBING-Rough 12/26/2025 Approved JEFFREY HARTLINE
Drywall Nailing 12/31/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Final 1/5/2026 Not Ready for Inspection JEFFREY HARTLINE
HVAC-Final 1/5/2026 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Final 2/17/2026 Approved JEFFREY HARTLINE
PLUMBING-Final 2/17/2026 Approved JEFFREY HARTLINE
Final 2/19/2026 OK to Issue CofO JEFFREY HARTLINE
Green Building Final 2/19/2026 Approved JEFFREY HARTLINE
HVAC-Final 2/19/2026 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 2/19/2026 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 2/19/2026 Approved JEFFREY HARTLINE