16033-16035 W JERSEY ST 91344
Certificate Information: 16033-16035 W JERSEY ST 91344
- Application / Permit
- 23016-20000-45152
- Plan Check / Job No.
- B23VN17727
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 18'1" X 20'4" ATTACHED GARAGE TO (N) JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22. WORK DONE PER WFPP AND ENGINEER DETAIL.
- Permit Issued
- Issued on 1/8/2024
- Issuing Office
- Current Status
- CofO Issued on 3/31/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2023 | KAMYAR EMAMI |
| Building Plans Picked Up | 1/3/2024 | APPLICANT |
| Issued | 1/8/2024 | APPLICANT |
| CofO in Progress | 3/12/2026 | CHRISTOPHER ROJAS |
| CofO Issued | 3/31/2026 | RUBEN SALAS |
| Permit Finaled | 3/31/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/3/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/3/2024 | LEE GUILBEAUX |
| Hold | Cleared | 7/8/2025 | CARMEN MERAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/11/2025 | Partial Inspection | KEVIN BERBERYAN |
| Deputy Drilled-In Anchors | 8/4/2025 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 8/6/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 8/6/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 8/8/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 8/8/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 8/13/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Sewer | 8/28/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 9/9/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 9/9/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 9/9/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Sewer | 9/9/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 9/16/2025 | Approved | CHRISTOPHER ROJAS |
| Wood Frame | 9/16/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 9/19/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 9/19/2025 | Conditional Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 9/29/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 9/29/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 9/29/2025 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Rough | 9/29/2025 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 10/7/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 12/17/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 12/17/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 12/17/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 12/17/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| MERV13>=Final | 12/17/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 12/17/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 12/17/2025 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 12/17/2025 | Approved | CHRISTOPHER ROJAS |
| Special/Order Compliance | 12/17/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 1/9/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 1/9/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 1/9/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Final | 1/9/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 3/10/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Final | 3/10/2026 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 3/12/2026 | Approved | CHRISTOPHER ROJAS |