15925-15927 W LIGGETT ST 91343

Certificate Information: 15925-15927 W LIGGETT ST 91343

Application / Permit
23016-20000-44901
Plan Check / Job No.
B23VN17614
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) - PER ENGINEER
Permit Issued
Issued on 2/20/2024
Issuing Office
Current Status
CofO Issued on 9/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2024 APPLICANT
Assigned to Plan Check Engineer 1/5/2024 ALEC MOUSAKHANIAN
Corrections Issued 1/6/2024 ALEC MOUSAKHANIAN
Plan Check Approved 2/18/2024 DANIEL ABRAMYAN
Issued 2/20/2024 APPLICANT
CofO in Progress 7/3/2025 SALVADOR MARTINEZ
Permit Finaled 9/9/2025 RUBEN SALAS
CofO Issued 9/9/2025 RUBEN SALAS
Permit Finaled 9/9/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/27/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 1/27/2024 CARLOS AGUILERA
Sewer availability Cleared 1/27/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/14/2024 CARLOS AGUILERA
Grading Pre-Inspection Cleared 2/15/2024 CHARLES POWELL

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/15/2024 Approved RAUL OLAGI
PLUMBING-Rough 4/1/2024 Corrections Issued SALVADOR MARTINEZ
Underground Mechanical 4/4/2024 Partial Approval MISAEL ESPARZA
Deputy Drilled-In Anchors 4/17/2024 Conditional Approval RAUL OLAGI
Wood Frame 4/22/2024 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 5/9/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 5/9/2024 Corrections Issued RAUL OLAGI
Green Building Rough 5/9/2024 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 5/9/2024 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 7/8/2024 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 7/8/2024 Approved RAUL OLAGI
HVAC-Rough 7/8/2024 Approved RAUL OLAGI
PLUMBING-Rough 7/8/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 7/31/2024 Partial Approval RAUL OLAGI
Green Building Rough 7/31/2024 Approved RAUL OLAGI
Insulation 7/31/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 7/31/2024 Partial Approval RAUL OLAGI
Drywall Nailing 10/9/2024 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 10/9/2024 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 1/30/2025 Approved RAUL OLAGI
Final 1/30/2025 Corrections Issued RAUL OLAGI
Green Building Final 1/30/2025 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 1/30/2025 SGSOV Approved RAUL OLAGI
Smoke Detectors 1/30/2025 Approved RAUL OLAGI
Final 6/13/2025 Corrections Issued JACK KARGODORIAN
Final 6/18/2025 Not Ready for Inspection MICHEL ABAJAN
Final 6/23/2025 Corrections Issued SALVADOR MARTINEZ
Final 6/27/2025 Not Ready for Inspection SALVADOR MARTINEZ
Service/Power Release 6/27/2025 Not Ready for Inspection SALVADOR MARTINEZ
Final 7/2/2025 OK to Issue CofO SALVADOR MARTINEZ
Service/Power Release 7/2/2025 Approved SALVADOR MARTINEZ