8980-8982 N MEGAN AVE 91304
Certificate Information: 8980-8982 N MEGAN AVE 91304
- Application / Permit
- 23016-20000-44794
- Plan Check / Job No.
- B23VN17548
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert (E) Attached Garage into (N) ADU per CA Govt. Code 65852.2(e)(1)(A). All work per WFPP
- Permit Issued
- Issued on 1/26/2024
- Issuing Office
- Current Status
- CofO Issued on 4/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2023 | AMY GUEVARRA |
| Corrections Issued | 1/4/2024 | AMY GUEVARRA |
| Applicant returned to address corrections | 1/17/2024 | ANGELICA DAVE |
| Plan Check Approved | 1/24/2024 | ALEC MOUSAKHANIAN |
| Issued | 1/26/2024 | APPLICANT |
| CofO in Progress | 4/5/2024 | JEFFREY HARTLINE |
| CofO Issued | 4/19/2024 | JOHN JANSON |
| Permit Finaled | 4/19/2024 | JOHN JANSON |
Permit Application Clearance Information
| ZA Case | Cleared | 1/10/2024 | NATHAN ROMINE |
| Address approval | Cleared | 1/11/2024 | NIKKI ZULUETA |
| BHO/Hillside ordinance | Cleared | 1/11/2024 | NIKKI ZULUETA |
| BHO/Hillside ordinance | Cleared | 1/11/2024 | NIKKI ZULUETA |
| BHO/Hillside ordinance | Cleared | 1/11/2024 | NIKKI ZULUETA |
| BHO/Hillside ordinance | Cleared | 1/11/2024 | NIKKI ZULUETA |
| BHO/Hillside ordinance | Cleared | 1/11/2024 | NIKKI ZULUETA |
| Sewer availability | Cleared | 1/11/2024 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2024 | NIKKI ZULUETA |
| Grading Pre-Inspection | Cleared | 1/18/2024 | MICHAEL TEMPLE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/13/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Pre-Inspection | 2/13/2024 | Partial Approval | JEFFREY HARTLINE |
| Underground Mechanical | 2/13/2024 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 2/15/2024 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 2/27/2024 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 2/27/2024 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 2/27/2024 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 2/27/2024 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 2/27/2024 | Partial Approval | JEFFREY HARTLINE |
| PLUMBING-Rough | 2/27/2024 | Approved | JEFFREY HARTLINE |
| Insulation | 2/29/2024 | Corrections Issued | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 3/4/2024 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 3/4/2024 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Rough | 3/4/2024 | Approved | JEFFREY HARTLINE |
| Insulation | 3/4/2024 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 3/4/2024 | Approved | JEFFREY HARTLINE |
| Shower Pan | 3/4/2024 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 3/7/2024 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Final | 4/1/2024 | Approved | JEFFREY HARTLINE |
| Final | 4/1/2024 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Final | 4/1/2024 | Approved | JEFFREY HARTLINE |
| HVAC-Final | 4/1/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 4/1/2024 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 4/1/2024 | SGSOV Approved | JEFFREY HARTLINE |
| Smoke Detectors | 4/1/2024 | Approved | JEFFREY HARTLINE |
| Final | 4/4/2024 | OK to Issue CofO | JEFFREY HARTLINE |