3675 W EDENHURST AVE 90039

Certificate Information: 3675 W EDENHURST AVE 90039

Application / Permit
23016-20000-44683
Plan Check / Job No.
B23VN17471
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing Garage (18' x 18') to an Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 2/14/2024
Issuing Office
Current Status
CofO Issued on 11/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2023 APPLICANT
Assigned to Plan Check Engineer 1/11/2024 VAHAN JIVALAGIAN
Corrections Issued 1/16/2024 VAHAN JIVALAGIAN
Quality Review Completed 1/19/2024 OMID HEDAYAT
Building Plans Picked Up 1/24/2024 APPLICANT
Applicant returned to address corrections 2/12/2024 VAHAN JIVALAGIAN
Plan Check Approved 2/14/2024 VAHAN JIVALAGIAN
Issued 2/14/2024 APPLICANT
CofO in Progress 11/15/2024 THOMAS LOGRASSO
Permit Finaled 11/16/2024 DEROLD HAUFF
CofO Issued 11/16/2024 DEROLD HAUFF
Permit Finaled 11/16/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/27/2024 AMBER CAMPBELL
Sewer availability Cleared 1/27/2024 AMBER CAMPBELL
Construction near power lines Cleared 1/29/2024 WALTER RAMIREZ
ZI Cleared 1/31/2024 DANIEL CORONADO
Eng Process Fee Ord 176,300 Cleared 2/13/2024 AMBER CAMPBELL

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/20/2024 Corrections Issued HAMIK HARTOUNIAN
Underground Mechanical 3/20/2024 Partial Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 5/15/2024 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 5/21/2024 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 5/28/2024 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 7/3/2024 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 7/3/2024 Approved ALIZAH MAYAGOITIA
HVAC-Rough 7/3/2024 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 7/3/2024 Approved ALIZAH MAYAGOITIA
Underground Mechanical 7/3/2024 Partial Approval ALIZAH MAYAGOITIA
Green Building Rough 7/9/2024 Approved THOMAS LOGRASSO
Insulation 7/9/2024 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 7/9/2024 Partial Approval THOMAS LOGRASSO
Shower Pan 7/9/2024 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 7/16/2024 Approved ENRIQUE MIRELES
Drywall Nailing 7/30/2024 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 7/30/2024 Approved THOMAS LOGRASSO
ELECTRICAL-Final 10/8/2024 Corrections Issued THOMAS LOGRASSO
Final 10/23/2024 Corrections Issued THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 10/23/2024 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 10/23/2024 Approved THOMAS LOGRASSO
Final 11/8/2024 Corrections Issued ROY SPAULDING
Green Building Final 11/8/2024 Not Ready for Inspection ROY SPAULDING
Final 11/14/2024 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 11/14/2024 Approved THOMAS LOGRASSO
Service/Power Release 11/14/2024 Approved THOMAS LOGRASSO