10147-10149 N COLUMBUS AVE 91345
Certificate Information: 10147-10149 N COLUMBUS AVE 91345
- Application / Permit
- 23016-20000-44671
- Plan Check / Job No.
- B23VN17457
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: CONVERT (E) ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER ENG.
- Permit Issued
- Issued on 3/11/2024
- Issuing Office
- Current Status
- CofO Issued on 10/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 12/25/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 3/1/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 3/10/2024 | ALFRED RAMIREZ |
| Issued | 3/11/2024 | APPLICANT |
| CofO in Progress | 10/18/2024 | JENNIFER RABUCHIN |
| Permit Finaled | 10/28/2024 | DANIEL ORRANTE |
| CofO Issued | 10/28/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/28/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/28/2023 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 12/28/2023 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/29/2023 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Azarbin,, Hamid; Lic. No.: C64515 | 22655 COVELLO ST WEST HILLS, CA 91307 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 3/13/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Pre-Inspection | 3/13/2024 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 3/27/2024 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 3/29/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 3/29/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/29/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Sewer | 4/9/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/22/2024 | Not Ready for Inspection | JOHN COLEMAN |
| PLUMBING-Rough | 5/22/2024 | Not Ready for Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 6/20/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/20/2024 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 6/20/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/20/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Deputy Wood Construction | 6/26/2024 | Conditional Approval | JOHN COLEMAN |
| BUILDING-Rough-Frame | 6/28/2024 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 6/28/2024 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 6/28/2024 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 7/15/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/15/2024 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Underground Mechanical | 7/15/2024 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 7/22/2024 | Partial Approval | JENNIFER RABUCHIN |
| Shower Pan | 7/22/2024 | Approved | JENNIFER RABUCHIN |
| Wood Frame | 7/22/2024 | Approved | JENNIFER RABUCHIN |
| Insulation | 7/24/2024 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 7/26/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Shower Pan | 7/26/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 8/2/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/25/2024 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 9/25/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 9/25/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 9/25/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 9/25/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 9/25/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 9/25/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/1/2024 | Approved | JENNIFER RABUCHIN |
| Final | 10/1/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 10/1/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 10/1/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/1/2024 | Approved | JENNIFER RABUCHIN |
| Final | 10/21/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| Gas Test | 10/23/2024 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 10/23/2024 | Approved | JENNIFER RABUCHIN |