11442 W KAMLOOPS PL 91342

Certificate Information: 11442 W KAMLOOPS PL 91342

Application / Permit
23016-20000-44641
Plan Check / Job No.
B23VN17437
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN CONVERT (E) DETACHED GARAGE TO ADU PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 6/3/2024
Issuing Office
Current Status
CofO Issued on 1/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/9/2024 APPLICANT
Assigned to Plan Check Engineer 1/12/2024 JOHNPAUL ISIP
Corrections Issued 1/16/2024 JOHNPAUL ISIP
Plan Check Approved 6/1/2024 JOHNPAUL ISIP
Issued 6/3/2024 APPLICANT
CofO in Progress 12/31/2024 MICHEL ABAJAN
Permit Finaled 1/17/2025 RUBEN SALAS
CofO Issued 1/17/2025 RUBEN SALAS
Permit Finaled 1/17/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/6/2024 LEE GUILBEAUX
Sewer availability Cleared 2/6/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 2/6/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 2/20/2024 LEE GUILBEAUX
Grading Pre-Inspection Cleared 2/20/2024 CHARLES POWELL
ZI Cleared 4/19/2024 MAYELA VILLA
Construction near power lines Cleared 5/29/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Hernandez,, Gerardo; Lic. No.: C78115 1426 E STUART AVE      WEST COVINA, CA 91791

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/12/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 6/12/2024 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 7/1/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 7/1/2024 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 7/1/2024 Partial Approval MICHEL ABAJAN
Green Building Rough 7/1/2024 Approved MICHEL ABAJAN
HVAC-Rough 7/1/2024 Approved MICHEL ABAJAN
MERV13>=Rough 7/1/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 7/1/2024 Approved MICHEL ABAJAN
Underground Mechanical 7/1/2024 Partial Approval MICHEL ABAJAN
Insulation 7/5/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 7/5/2024 Approved MICHEL ABAJAN
Shower Pan 7/5/2024 Approved MICHEL ABAJAN
Drywall Nailing 7/10/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 7/10/2024 Approved MICHEL ABAJAN
Final 8/29/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 8/29/2024 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Final 8/29/2024 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 8/29/2024 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 8/29/2024 Not Ready for Inspection MISAEL ESPARZA
Final 10/15/2024 Corrections Issued ROBERT GOLD
Green Building Final 10/15/2024 Approved ROBERT GOLD
MERV13>=Final 10/15/2024 Approved ROBERT GOLD
Smoke Detectors 10/15/2024 Approved ROBERT GOLD
ELECTRICAL-Final 12/12/2024 Approved MICHEL ABAJAN
Final 12/12/2024 Corrections Issued MICHEL ABAJAN
HVAC-Final 12/12/2024 Approved MICHEL ABAJAN
PLUMBING-Final 12/12/2024 Approved MICHEL ABAJAN
Final 12/30/2024 OK to Issue CofO MICHEL ABAJAN