7650 N VAN NUYS BLVD 91405
Certificate Information: 7650 N VAN NUYS BLVD 91405
- Application / Permit
- 23016-20000-44600
- Plan Check / Job No.
- B23VN17413
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EPLAN INSTALL BALLASTED PV SYSTEM TO APARTMENT BUILDING
- Permit Issued
- Issued on 3/6/2024
- Issuing Office
- Current Status
- Permit Finaled on 12/9/2024
Permit Application Status History
| Submitted | 1/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2024 | RAPHAEL ROSAS |
| Corrections Issued | 1/17/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 1/18/2024 | STEVEN KIM |
| Assigned to Zoning Architect | 1/19/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 2/21/2024 | RAPHAEL ROSAS |
| Issued | 3/6/2024 | APPLICANT |
| Permit Finaled | 12/9/2024 | KENNETH ROBERTS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 1/30/2024 | BRENNEN OBETO |
| Miscellaneous | Cleared | 1/30/2024 | BRENNEN OBETO |
| ZA Case | Cleared | 1/30/2024 | BRENNEN OBETO |
| Miscellaneous | Cleared | 2/21/2024 | FIRE DEPARTMENT |
| Zoning Plan Check | Cleared | 2/21/2024 | Gurunath Nesarajah |
Contact Information
| Contractor | Solarco Energy; Lic. No.: 1001001-C46 | 22982 LA CADENA DR STE 219 LAGUNA HILLS, CA 92653 |
| Engineer | Wyssling,, Scott E; Lic. No.: C83664 | 76 N MEADOWBROOK DR ALPINE, UT 84004 |
Inspector Information
| SEAN GRIFFITH, (818) 374-1102 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 10/4/2024 | Not Ready for Inspection | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 10/4/2024 | SGSOV Not Ready | KENNETH ROBERTS |
| Smoke Detectors | 10/4/2024 | Not Ready for Inspection | KENNETH ROBERTS |
| Deputy Other (see comments) | 11/1/2024 | Conditional Approval | ROBERT DAVIS |
| Final | 11/4/2024 | Partial Inspection | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 11/4/2024 | SGSOV Approved | ANDREW DORSO |
| Final | 11/8/2024 | Conditional Approval | KENNETH ROBERTS |
| Final | 11/13/2024 | Not Ready for Inspection | KENNETH ROBERTS |
| Final | 12/2/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Special/Order Compliance | 12/3/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Special/Order Compliance | 12/4/2024 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Final | 12/9/2024 | Permit Finaled | KENNETH ROBERTS |