3400 S FIGUEROA ST 90007
Certificate Information: 3400 S FIGUEROA ST 90007
- Application / Permit
- 23016-20000-44595
- Plan Check / Job No.
- B23VN17412
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (4) Sports Arena (unlimited seating capacity)
- Work Description
- TENANT IMPROVEMENT - NON-STRUCTURAL REMODEL TO CORE AND SHELL SPACE OF (E) SPORTS ARENA TO CONTROL ROOM, AV ROOM AND ELECTRICAL/MECHANICAL ROOMS. NO CHANGE OF USE/PARKING
- Permit Issued
- Issued on 2/23/2024
- Issuing Office
- Current Status
- Permit Finaled on 9/12/2025
Permit Application Status History
| Submitted | 12/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2023 | GURUNATH NESARAJAH |
| Corrections Issued | 12/23/2023 | GURUNATH NESARAJAH |
| Plan Check Approved | 2/19/2024 | GURUNATH NESARAJAH |
| Issued | 2/23/2024 | APPLICANT |
| Permit Finaled | 9/9/2025 | ALFREDO LOPEZ |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/5/2024 | MANERI ROMAN |
| Redevelopment Project Area | Cleared | 1/11/2024 | ELIZABETH GALLARDO |
Contact Information
| Architect | Parab,, Sunil; Lic. No.: NA26944 | , |
| Contractor | Pinnacle Contracting Corporation; Lic. No.: 665647-B | 21800 BURBANK BLVD #210 WOODLAND HILLS, CA 91367 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 4/12/2024 | Partial Approval | ALFREDO LOPEZ |
| Insulation | 4/24/2024 | Partial Approval | ALFREDO LOPEZ |
| Insulation | 4/29/2024 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 5/1/2024 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 5/6/2024 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 5/20/2024 | Partial Approval | ALFREDO LOPEZ |
| Excavation/Setback/Form/Re-Bar | 5/31/2024 | Approved | ALFREDO LOPEZ |
| T-Bar Ceiling | 6/25/2024 | Partial Approval | ALFREDO LOPEZ |
| Special/Order Compliance | 7/25/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| T-Bar Ceiling | 7/25/2024 | Approved | ALFREDO LOPEZ |
| Deputy Drilled-In Anchors | 7/31/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Drywall Nailing | 8/2/2024 | Partial Inspection | ALFREDO LOPEZ |
| Drywall Nailing | 8/6/2024 | Partial Approval | ALFREDO LOPEZ |
| Final | 9/9/2025 | Permit Finaled | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/9/2025 | SGSOV Not Required | ALFREDO LOPEZ |