13552-13554 W CANTARA ST 91402
Certificate Information: 13552-13554 W CANTARA ST 91402
- Application / Permit
- 23016-20000-44397
- Plan Check / Job No.
- B23VN17305
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 12/27/2023
- Issuing Office
- Current Status
- CofO Issued on 5/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 12/26/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 12/26/2023 | APPLICANT |
| Issued | 12/27/2023 | APPLICANT |
| CofO in Progress | 5/8/2024 | GREGG CUMMINGS |
| Permit Finaled | 5/10/2024 | RUBEN SALAS |
| CofO Issued | 5/10/2024 | RUBEN SALAS |
| Permit Finaled | 5/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/27/2023 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2023 | JOHN LIN |
| Sewer availability | Cleared | 12/27/2023 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/3/2024 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 1/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 1/25/2024 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 1/25/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 1/25/2024 | Partial Approval | GREGG CUMMINGS |
| Sewer | 1/25/2024 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 2/9/2024 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 2/9/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 2/9/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 2/9/2024 | Approved | GREGG CUMMINGS |
| Structural Steel Frame | 2/14/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 2/16/2024 | Corrections Issued | GREGG CUMMINGS |
| Insulation | 2/16/2024 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 2/20/2024 | No Access for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 2/20/2024 | No Access for Inspection | MATTHEW NELSON |
| Green Building Rough | 2/20/2024 | No Access for Inspection | MATTHEW NELSON |
| HVAC-Rough | 2/20/2024 | No Access for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/22/2024 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 2/22/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 2/22/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 2/23/2024 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 2/26/2024 | Approved | GREGG CUMMINGS |
| Green Building Rough | 2/26/2024 | Approved | GREGG CUMMINGS |
| Insulation | 2/26/2024 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 2/29/2024 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 2/29/2024 | Corrections Issued | THOMAS FINNILA |
| Shower Pan | 2/29/2024 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 3/5/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 3/11/2024 | Approved | MATTHEW NELSON |
| Final | 5/1/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 5/1/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 5/1/2024 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 5/1/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 5/7/2024 | Approved | GREGG CUMMINGS |
| Final | 5/7/2024 | OK to Issue CofO | GREGG CUMMINGS |
| Green Building Final | 5/7/2024 | Approved | GREGG CUMMINGS |
| HVAC-Final | 5/7/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 5/7/2024 | Approved | GREGG CUMMINGS |