214 S TAVISTOCK AVE 90049

Certificate Information: 214 S TAVISTOCK AVE 90049

Application / Permit
23016-20000-44203
Plan Check / Job No.
B23VN17213
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED 20'4"X20'1" GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d). CONSTRUCTION DESIGN PER ENGR.
Permit Issued
Issued on 1/23/2024
Issuing Office
Valley
Current Status
CofO Issued on 6/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2023 APPLICANT
Assigned to Plan Check Engineer 12/19/2023 HAYATO TSUCHIYA
Corrections Issued 12/19/2023 HAYATO TSUCHIYA
Building Plans Picked Up 1/3/2024 APPLICANT
Issued 1/23/2024 APPLICANT
CofO in Progress 6/12/2024 CARLOS MATAMOROS
Permit Finaled 6/14/2024 DANIEL ORRANTE
CofO Issued 6/14/2024 DANIEL ORRANTE
Permit Finaled 6/14/2024 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/12/2024 VASIL MIHALEV
Specific Plan Cleared 1/17/2024 EDUARDO HERMOSO
Address approval Cleared 1/18/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 1/18/2024 DARIN LAM
Sewer availability Cleared 1/18/2024 DARIN LAM

Contact Information

Contractor Trig Builders Inc; Lic. No.: 1030887-B 6442 COLDWATER CANYON AVE 111      NORTH HOLLYWOOD, CA 91606
Engineer Nirattisai,, Preston; Lic. No.: C85115 28411 ASCENT WAY      SANTA CLARITA, CA 91350

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/22/2024 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 2/22/2024 Approved CARLOS MATAMOROS
Gas Test 3/21/2024 Approved CARLOS MATAMOROS
HVAC-Rough 3/21/2024 Approved CARLOS MATAMOROS
PLUMBING-Rough 3/21/2024 Approved CARLOS MATAMOROS
Underground Mechanical 3/21/2024 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 3/28/2024 Corrections Issued MICHAEL PELHAM
Green Building Rough 3/28/2024 Corrections Issued MICHAEL PELHAM
BUILDING-Rough-Frame 4/2/2024 Partial Approval CHRISTOPHER WILSON
Green Building Rough 4/2/2024 Not Ready for Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 4/2/2024 Not Ready for Inspection CHRISTOPHER WILSON
Shower Pan 4/2/2024 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 4/9/2024 Approved CHRISTOPHER WILSON
Green Building Rough 4/9/2024 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 4/9/2024 Approved CHRISTOPHER WILSON
Shower Pan 4/9/2024 Approved CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 4/15/2024 Approved CARLOS MATAMOROS
Insulation 4/15/2024 Approved CARLOS MATAMOROS
Drywall Nailing 4/25/2024 Approved CARLOS MATAMOROS
ELECTRICAL-Final 6/10/2024 Approved CARLOS MATAMOROS
Final 6/10/2024 OK to Issue CofO CARLOS MATAMOROS
Green Building Final 6/10/2024 Approved CARLOS MATAMOROS
HVAC-Final 6/10/2024 Approved CARLOS MATAMOROS
PLUMBING-Final 6/10/2024 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 6/10/2024 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 6/10/2024 Approved CARLOS MATAMOROS