7835-7837 N VICKY AVE 91304

Certificate Information: 7835-7837 N VICKY AVE 91304

Application / Permit
23016-20000-44163
Plan Check / Job No.
B23VN17187
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert existing attached garage to new attached accessory dwelling unit per LAMC 12.22 A.33(c) and (e).
Permit Issued
Issued on 1/16/2024
Issuing Office
Current Status
CofO Issued on 7/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/14/2023 APPLICANT
Assigned to Plan Check Engineer 12/19/2023 RAMA DABADGE
Corrections Issued 12/20/2023 RAMA DABADGE
Building Plans Picked Up 12/27/2023 APPLICANT
Plan Check Approved 1/16/2024 ALEC MOUSAKHANIAN
Issued 1/16/2024 APPLICANT
CofO in Progress 6/18/2024 CHRIS CHRISTENSEN
Permit Finaled 7/2/2024 JOHN JANSON
CofO Issued 7/2/2024 JOHN JANSON
Permit Finaled 7/2/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/27/2023 CARLOS AGUILERA
Sewer availability Cleared 12/27/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/28/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/15/2024 Approved JEFFREY HARTLINE
Deputy Drilled-In Anchors 2/16/2024 Conditional Approval JEFFREY HARTLINE
Excavation/Setback/Form/Re-Bar 2/20/2024 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 2/20/2024 Approved CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 2/23/2024 Conditional Approval JEFFREY HARTLINE
ELECTRICAL-Rough 3/15/2024 Approved CHRIS CHRISTENSEN
HVAC-Rough 3/15/2024 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Rough 3/15/2024 Approved CHRIS CHRISTENSEN
Wood Frame 3/15/2024 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 3/22/2024 Approved CHRIS CHRISTENSEN
Wood Frame 3/22/2024 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 3/27/2024 Approved CHRIS CHRISTENSEN
Green Building Rough 3/27/2024 Approved CHRIS CHRISTENSEN
Insulation 3/27/2024 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 3/27/2024 Corrections Issued CHRIS CHRISTENSEN
Shower Pan 3/27/2024 Approved CHRIS CHRISTENSEN
Drywall Nailing 4/3/2024 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 4/3/2024 Approved CHRIS CHRISTENSEN
Wood Frame 4/3/2024 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 6/11/2024 Approved CHRIS CHRISTENSEN
Final 6/11/2024 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 6/11/2024 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Final 6/11/2024 Approved CHRIS CHRISTENSEN
PLUMBING-Final 6/11/2024 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 6/11/2024 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 6/11/2024 Approved CHRIS CHRISTENSEN
Final 6/17/2024 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 6/17/2024 Approved CHRIS CHRISTENSEN