10649 N NASSAU AVE 91040
Certificate Information: 10649 N NASSAU AVE 91040
- Application / Permit
- 23016-20000-44144
- Plan Check / Job No.
- B23VN17172
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER 65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 6/5/2024
- Issuing Office
- Current Status
- Issued on 6/5/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 12/19/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 1/18/2024 | APPLICANT |
| Issued | 6/5/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/3/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/3/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/4/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Cuco Rios & Sons Construction; Lic. No.: 1015630-B | 639 S GLENWOOD PLACE STE 200B BURBANK, CA 91506 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/3/2024 | Conditional Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 9/6/2024 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 10/22/2024 | Corrections Issued | WILLIAM WREN |
| Deputy Drilled-In Anchors | 11/6/2024 | Conditional Approval | WILLIAM WREN |
| ELECTRICAL-Rough | 11/8/2024 | Approved | WILLIAM WREN |
| Green Building Rough | 11/8/2024 | Not Ready for Inspection | WILLIAM WREN |
| HVAC-Rough | 11/8/2024 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 11/8/2024 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 11/26/2024 | Approved | WILLIAM WREN |
| Green Building Rough | 11/26/2024 | Approved | WILLIAM WREN |
| HVAC-Rough | 11/26/2024 | Approved | WILLIAM WREN |
| Insulation | 12/4/2024 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2024 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/31/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Drywall Nailing | 12/31/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/31/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| Shower Pan | 12/31/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| Drywall Nailing | 1/29/2025 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 1/29/2025 | Approved | WILLIAM WREN |
| Shower Pan | 1/29/2025 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 5/23/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 5/23/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 5/23/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 5/23/2025 | SGSOV Not Ready | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 5/23/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 5/30/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Final | 5/30/2025 | Not Ready for Inspection | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 5/30/2025 | SGSOV Approved | DAVID ANDERSON |