5709-5711 N RAWLINGS AVE 91367
Certificate Information: 5709-5711 N RAWLINGS AVE 91367
- Application / Permit
- 23016-20000-44086
- Plan Check / Job No.
- B23VN17144
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXTERIOR AND INTERIOR ALTERATION/REMODEL AND CONVERT TWO STORY PORTION OF (E) SFD INTO (N) 778 SF 2 STORY ADU PER GCS 65852.2(e)(1)(A) ALL WORK PER ENG.
- Permit Issued
- Issued on 1/8/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2023 | RAMA DABADGE |
| Corrections Issued | 12/20/2023 | RAMA DABADGE |
| Building Plans Picked Up | 12/26/2023 | APPLICANT |
| Issued | 1/8/2024 | APPLICANT |
| CofO in Progress | 6/10/2024 | ARUTYUN MADATYAN |
| CofO Issued | 6/17/2024 | JOHN JANSON |
| Permit Finaled | 6/17/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/27/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 12/27/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/19/2024 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2024 | Partial Approval | JEFFREY PARD |
| PLUMBING-Rough | 2/13/2024 | Partial Approval | ALEXANDER HANDY |
| Sewer | 2/13/2024 | Approved | ALEXANDER HANDY |
| Rough-Elec/Plmb/HVAC | 2/22/2024 | Partial Approval | ARUTYUN MADATYAN |
| Wood Frame | 2/22/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 2/27/2024 | Approved | ARUTYUN MADATYAN |
| Wood Frame | 2/27/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Deputy Wood Construction | 2/29/2024 | Conditional Approval | ALEXANDER HANDY |
| Interior/Exterior Lathing | 3/15/2024 | Partial Approval | ALEXANDER HANDY |
| Insulation | 3/21/2024 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 3/27/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 4/9/2024 | Partial Approval | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 6/4/2024 | Approved | ARUTYUN MADATYAN |
| Final | 6/4/2024 | Corrections Issued | ARUTYUN MADATYAN |
| HVAC-Final | 6/4/2024 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 6/4/2024 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Smoke Detectors | 6/4/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 6/7/2024 | Approved | ARUTYUN MADATYAN |
| Final | 6/7/2024 | OK to Issue CofO | ARUTYUN MADATYAN |
| PLUMBING-Final | 6/7/2024 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 6/7/2024 | SGSOV Approved | ARUTYUN MADATYAN |