6320-6324 S BROADWAY 90003

Certificate Information: 6320-6324 S BROADWAY 90003

Application / Permit
23016-20000-43945
Plan Check / Job No.
B23VN17065
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan: exterior and interior alterations to an existing 18 unit 2 story apartment to alter floor lay out, and change out /replace existing windows remove the parking count per AB2097. alteration to the existing site to upgrade accessibility. reroofing of existing roof (no change in framing)
Permit Issued
Issued on 9/6/2024
Issuing Office
Current Status
Issued on 9/6/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/14/2023 APPLICANT
Assigned to Plan Check Engineer 1/4/2024 MINA HABIB
Corrections Issued 1/12/2024 MINA HABIB
Quality Review Completed 1/17/2024 RODOLFO ARIAS
Applicant returned to address corrections 4/23/2024 MINA HABIB
Applicant returned to address corrections 4/24/2024 MINA HABIB
Applicant returned to address corrections 6/14/2024 MINA HABIB
Applicant returned to address corrections 6/18/2024 MINA HABIB
Applicant returned to address corrections 6/20/2024 MINA HABIB
Applicant returned to address corrections 7/11/2024 MINA HABIB
Applicant returned to address corrections 7/12/2024 MINA HABIB
Applicant returned to address corrections 8/9/2024 MINA HABIB
Plan Check Approved 8/29/2024 MINA HABIB
Issued 9/6/2024 APPLICANT

Permit Application Clearance Information

Tenant Habitability Plan Cleared 2/9/2024 RICARDO BOHORQUEZ
Roof/Waste drainage to street Cleared 3/19/2024 JUSTIN BICOL
Sewer availability Cleared 3/19/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 3/26/2024 JUSTIN BICOL
Green Code Cleared 4/16/2024 MICHAEL AYERS
Public Housing Cleared 4/19/2024 DANIEL COLLINS
Historic Resource Verification Cleared 4/24/2024 RAFAEL FONTES
DAS Clearance Cleared 8/12/2024 Eugene Barbeau
Redevelopment Project Area Cleared 8/20/2024 ELIZABETH GALLARDO
Community Plan Implem. Overlay Cleared 8/28/2024 ANACANY HURTADO

Contact Information

Architect Musser,, David Charles; Lic. No.: C15234 320 E GREENWOOD AVE      LA HABRA, CA 90631
Contractor Precision General Commercial Contractors Inc; Lic. No.: 790153-B 7250 REDWOOD BLVD STE 214      NOVATO, CA 94945

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 11/27/2024 Approved DARRYL ARNOLD
Pre-Inspection 11/27/2024 Corrections Issued DARRYL ARNOLD
Wood Frame 11/27/2024 Conditional Approval DARRYL ARNOLD
Drywall Nailing 12/5/2024 Partial Inspection ALFREDO LOPEZ
Wood Frame 12/5/2024 Partial Inspection ALFREDO LOPEZ
Drywall Nailing 12/12/2024 Not Ready for Inspection DARRYL ARNOLD
Pre-Inspection 12/12/2024 Not Ready for Inspection DARRYL ARNOLD
Insulation 12/13/2024 Corrections Issued DARRYL ARNOLD
Drywall Nailing 1/10/2025 Approved DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 2/20/2025 Not Ready for Inspection ALFREDO LOPEZ
Floor/Roof Diaphrgm/Shear Wall 2/21/2025 Not Ready for Inspection ALFREDO LOPEZ
Floor/Roof Diaphrgm/Shear Wall 2/26/2025 Partial Approval ALFREDO LOPEZ
Pre-Inspection 3/7/2025 Not Ready for Inspection ALFREDO LOPEZ
Final 12/29/2025 Not Ready for Inspection DARRYL ARNOLD
Green Building Final 12/29/2025 Not Ready for Inspection ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 12/29/2025 SGSOV Not Ready ALFREDO LOPEZ
Smoke Detectors 12/29/2025 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 12/29/2025 Approved ALFREDO LOPEZ
Drywall Nailing 12/31/2025 Corrections Issued DARRYL ARNOLD