235 W 47TH ST 90037
Certificate Information: 235 W 47TH ST 90037
- Application / Permit
- 23016-20000-43935
- Plan Check / Job No.
- B23VN17059
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EXTERIOR AND INTERIOR ALTERATION TO EXISTING TWO STORY 8 UNIT APARTMENT BUILDING. CHANGE FLOOR LAY OUT AND REMODEL EXISTING UNITS. ADD A NEW RAMP, REPLACE EXISTING ROOFING AND REMOVE THE PARKING PER AB2097 (see comments)
- Permit Issued
- Issued on 9/4/2024
- Issuing Office
- Current Status
- Issued on 9/4/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2024 | MINA HABIB |
| Corrections Issued | 1/17/2024 | MINA HABIB |
| Quality Review Completed | 1/19/2024 | RODOLFO ARIAS |
| Applicant returned to address corrections | 4/24/2024 | MINA HABIB |
| Applicant returned to address corrections | 4/26/2024 | MINA HABIB |
| Applicant returned to address corrections | 7/26/2024 | MINA HABIB |
| Applicant returned to address corrections | 7/30/2024 | MINA HABIB |
| Applicant returned to address corrections | 8/12/2024 | MINA HABIB |
| Plan Check Approved | 9/3/2024 | MINA HABIB |
| Issued | 9/4/2024 | APPLICANT |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 2/9/2024 | RICARDO BOHORQUEZ |
| Sewer availability | Cleared | 3/20/2024 | DAVID LOPEZ |
| Prkng lot landscape/Water mgmt | Cleared | 4/1/2024 | MATHEW QUAN |
| Green Code | Cleared | 4/16/2024 | MICHAEL AYERS |
| DAS Clearance | Cleared | 8/8/2024 | Eugene Barbeau |
| Public Housing | Cleared | 8/15/2024 | JOEL LAUNCHBAUGH |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2024 | JOSE HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 8/23/2024 | ADRIAN SANCHEZ |
Contact Information
| Architect | Musser,, David Charles; Lic. No.: C15234 | 320 E GREENWOOD AVE LA HABRA, CA 90631 |
| Contractor | Precision General Commercial Contractors Inc; Lic. No.: 790153-B | 7250 REDWOOD BLVD STE 214 NOVATO, CA 94945 |
| Engineer | Burica,, Michael Jerome; Lic. No.: C57151 | 9283 RESEARCH DR IRVINE, CA 92618 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/22/2025 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 1/22/2025 | Approved | DARRYL ARNOLD |
| Insulation | 1/24/2025 | Off-Hour Fees Due | |
| Pre-Inspection | 2/20/2025 | Partial Inspection | ALFREDO LOPEZ |
| Wood Frame | 3/12/2025 | No Access for Inspection | ALFREDO LOPEZ |
| Wood Frame | 3/17/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 3/19/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 3/20/2025 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 3/25/2025 | Partial Approval | ALFREDO LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2025 | Partial Approval | ALFREDO LOPEZ |
| Excavation/Setback/Form/Re-Bar | 6/23/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 6/23/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Excavation/Setback/Form/Re-Bar | 6/30/2025 | Partial Approval | ALFREDO LOPEZ |
| Masonry Wall/Backfill | 7/3/2025 | Partial Approval | JEROME BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 7/7/2025 | Partial Approval | ALFREDO LOPEZ |
| Pre-Inspection | 7/7/2025 | Partial Approval | ALFREDO LOPEZ |
| Wood Frame | 7/29/2025 | Approved | DARRYL ARNOLD |
| Drywall Nailing | 8/4/2025 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 8/14/2025 | Partial Approval | ALFREDO LOPEZ |
| Final | 12/29/2025 | Partial Inspection | ALFREDO LOPEZ |
| Green Building Final | 12/29/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 12/29/2025 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 12/29/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 12/31/2025 | Corrections Issued | DARRYL ARNOLD |
| Green Building Final | 12/31/2025 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 12/31/2025 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 12/31/2025 | Conditional Approval | DARRYL ARNOLD |