7876 N VAN NUYS BLVD 91402
Certificate Information: 7876 N VAN NUYS BLVD 91402
- Application / Permit
- 23016-20000-43860
- Plan Check / Job No.
- B23VN17028
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (21) Motion Picture Theatre
- Work Description
- TENANT IMPROVEMENT TO EXISTING 2-STORY MOVIE THEATRE TO REMODEL LOBBY, CONCESSION AREA AND RESTROOM/THEATRE CORRIDORS.
- Permit Issued
- Issued on 4/15/2024
- Issuing Office
- Current Status
- Permit Finaled on 3/20/2025
Permit Application Status History
| Submitted | 12/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2024 | PETER MOSESIAN |
| Assigned to Zoning Architect | 1/11/2024 | PETER MOSESIAN |
| Corrections Issued | 1/19/2024 | PETER MOSESIAN |
| Quality Review Completed | 1/31/2024 | OMID HEDAYAT |
| Plan Check Approved | 4/5/2024 | PETER MOSESIAN |
| Issued | 4/15/2024 | APPLICANT |
| Permit Finaled | 3/20/2025 | ANDREW DORSO |
Permit Application Clearance Information
| "Q" conditions | Cleared | 1/26/2024 | ALEX VELA |
| Green Code | Cleared | 2/14/2024 | MICHAEL AYERS |
| Comm Cor/Mini-Mall | Cleared | 3/7/2024 | ALEX VELA |
| Comm Cor/Mini-Mall | Cleared | 3/8/2024 | STEVEN WECHSLER |
| Comm Cor/Mini-Mall | Cleared | 3/8/2024 | STEVEN WECHSLER |
| ZA Case | Cleared | 3/8/2024 | ALEX VELA |
| ZI | Cleared | 3/18/2024 | OLGA AYALA |
| DAS Clearance | Cleared | 3/26/2024 | Samuel Gonzalez |
| Zoning Plan Check | Cleared | 4/2/2024 | Samuel Gonzalez |
Contact Information
| Contractor | Ranack Corporation Of Colorado; Lic. No.: 627497-B | 652 SOUTH COUNTRY ROAD 9E LOVELAND, CO 80537 |
| Engineer | Deems,, Brandon; Lic. No.: S5352 | 1478 STONE POINT DR STE 320 ROSEVILLE, CA 95661 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 4/18/2024 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 4/22/2024 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 5/9/2024 | Partial Approval | DANNY RODRIGUEZ |
| Wood Frame | 5/16/2024 | Not Ready for Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 5/21/2024 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 5/29/2024 | Partial Inspection | ANDREW DORSO |
| Final | 6/28/2024 | Partial Inspection | ANDREW DORSO |
| Green Building Final | 6/28/2024 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 6/28/2024 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 6/28/2024 | Partial Inspection | ANDREW DORSO |
| Deputy Reinf. Concrete | 8/13/2024 | Conditional Approval | ANDREW DORSO |
| Footing/Foundation/Slab | 8/13/2024 | Partial Inspection | ANDREW DORSO |
| Reinforced Concrete Frame | 8/13/2024 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 9/25/2024 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 10/1/2024 | Not Ready for Inspection | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 10/4/2024 | Partial Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 10/4/2024 | Partial Inspection | ANDREW DORSO |
| Reinforced Concrete Frame | 10/4/2024 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 10/8/2024 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 10/10/2024 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 10/18/2024 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 11/5/2024 | Partial Inspection | ANDREW DORSO |
| T-Bar Ceiling | 11/5/2024 | Not Ready for Inspection | ANDREW DORSO |
| Deputy Drilled-In Anchors | 12/10/2024 | Approved | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 12/10/2024 | Approved | ANDREW DORSO |
| Light Gage Steel Frame | 12/10/2024 | Approved | ANDREW DORSO |
| T-Bar Ceiling | 12/10/2024 | Corrections Issued | ANDREW DORSO |
| Drywall Nailing | 12/16/2024 | Approved | ANDREW DORSO |
| Partition/T-Bar Ceiling | 12/16/2024 | Approved | ANDREW DORSO |
| Final | 2/14/2025 | Not Ready for Inspection | ANDREW DORSO |
| Smoke Detectors | 2/14/2025 | Approved | ANDREW DORSO |
| Final | 2/26/2025 | Not Ready for Inspection | ANDREW DORSO |
| Final | 3/17/2025 | Partial Inspection | DANNY RODRIGUEZ |
| Final | 3/20/2025 | Permit Finaled | ANDREW DORSO |