17557 1/2 W BALTAR ST 91325

Certificate Information: 17557 1/2 W BALTAR ST 91325

Application / Permit
23016-20000-43648
Plan Check / Job No.
B23VN16950
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert Existing (20' x 18') Garage into an Accessory Dwelling Unit per LAMC 12.22 A.33 (c) - (d). Work per Wood Frame Prescriptive Provisions.
Permit Issued
Issued on 3/13/2024
Issuing Office
Valley
Current Status
CofO Issued on 12/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/11/2023 APPLICANT
Assigned to Plan Check Engineer 12/14/2023 VAHAN JIVALAGIAN
Corrections Issued 12/15/2023 VAHAN JIVALAGIAN
Quality Review Completed 12/18/2023 OMID HEDAYAT
Building Plans Picked Up 12/28/2023 APPLICANT
Applicant returned to address corrections 1/31/2024 VAHAN JIVALAGIAN
Applicant returned to address corrections 2/23/2024 VAHAN JIVALAGIAN
Plan Check Approved 3/13/2024 VAHAN JIVALAGIAN
Issued 3/13/2024 APPLICANT
CofO in Progress 12/17/2024 RAUL OLAGI
Permit Finaled 12/18/2024 RUBEN SALAS
CofO Issued 12/18/2024 RUBEN SALAS
Permit Finaled 12/18/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/27/2023 CARLOS RAMIREZ
Sewer availability Cleared 12/27/2023 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 2/23/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/22/2024 Approved SALVADOR MARTINEZ
Sewer 4/4/2024 Approved SALVADOR MARTINEZ
Underground Mechanical 4/4/2024 Approved SALVADOR MARTINEZ
Deputy Drilled-In Anchors 4/9/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 4/9/2024 Approved RAUL OLAGI
Underground Mechanical 4/11/2024 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 5/15/2024 Not Ready for Inspection RAUL OLAGI
Green Building Rough 5/15/2024 Not Ready for Inspection RAUL OLAGI
ELECTRICAL-Rough 5/31/2024 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 5/31/2024 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 5/31/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 6/12/2024 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 6/12/2024 Approved RAUL OLAGI
HVAC-Rough 6/12/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 7/16/2024 Approved RAUL OLAGI
Green Building Rough 7/16/2024 Approved RAUL OLAGI
Insulation 7/16/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 7/16/2024 Partial Approval RAUL OLAGI
Shower Pan 7/16/2024 Approved RAUL OLAGI
Drywall Nailing 7/22/2024 Approved RAUL OLAGI
ELECTRICAL-Final 12/5/2024 Corrections Issued SALVADOR MARTINEZ
Final 12/5/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Final 12/5/2024 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Final 12/5/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Final 12/5/2024 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 12/5/2024 SGSOV Approved SALVADOR MARTINEZ
Smoke Detectors 12/5/2024 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 12/11/2024 Corrections Issued SALVADOR MARTINEZ
Final 12/11/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Final 12/11/2024 Approved SALVADOR MARTINEZ
HVAC-Final 12/11/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Final 12/11/2024 Approved SALVADOR MARTINEZ
Final 12/16/2024 OK to Issue CofO RAUL OLAGI