6410 N PLATT AVE 91307
Certificate Information: 6410 N PLATT AVE 91307
- Application / Permit
- 23016-20000-43065
- Plan Check / Job No.
- B23VN16702
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- EPLAN: TI to existing commercial consisting of +/- 560 linear feet of exterior faade remodel. Portions of the existing exterior front faade will be demolished and new facades will be rebuilt.
- Permit Issued
- Issued on 2/5/2025
- Issuing Office
- Current Status
- Permit Finaled on 10/1/2025
Permit Application Status History
| Submitted | 12/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/21/2023 | ARSALAN SHABESTARI |
| Assigned to Zoning Architect | 12/21/2023 | ARSALAN SHABESTARI |
| Corrections Issued | 12/23/2023 | ARSALAN SHABESTARI |
| Quality Review Completed | 1/3/2024 | YOUNG KIM |
| Plan Check Approved | 2/3/2025 | ARSALAN SHABESTARI |
| Issued | 2/5/2025 | APPLICANT |
| Permit Finaled | 9/30/2025 | BRIAN KELLY |
Permit Application Clearance Information
| ZA Case | Cleared | 1/9/2024 | ASHLEY RODARTE |
| "Q" conditions | Cleared | 1/10/2024 | ASHLEY RODARTE |
| "T" removal | Cleared | 1/10/2024 | ASHLEY RODARTE |
| Green Code | Cleared | 1/10/2024 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 2/21/2024 | KURT CORRAL |
| DAS Clearance | Cleared | 2/23/2024 | Gurunath Nesarajah |
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2024 | CARLOS AGUILERA |
| Highway dedication | Cleared | 3/1/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/1/2024 | CARLOS AGUILERA |
| Fire Marshal Fire Life Safety | Cleared | 3/21/2024 | WILLIAM JOHNS |
| Low Impact Development (LID) | Cleared | 1/6/2025 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 1/9/2025 | CARLOS AGUILERA |
| Zoning Plan Check | Cleared | 2/3/2025 | Gurunath Nesarajah |
Contact Information
| Contractor | Lyle Parks Jr Construction A California Partnership; Lic. No.: 858603-B | , |
| Contractor | Lyle Parks, Jr. Construction; Lic. No.: 858603-B | , |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/27/2025 | Partial Inspection | BRIAN KELLY |
| Deputy Reinf. Concrete | 4/7/2025 | Conditional Approval | BRIAN KELLY |
| Footing/Foundation/Slab | 4/7/2025 | Partial Inspection | BRIAN KELLY |
| Reinforced Concrete Frame | 4/7/2025 | Partial Inspection | BRIAN KELLY |
| Footing/Foundation/Slab | 4/8/2025 | Not Ready for Inspection | BRIAN KELLY |
| Reinforced Concrete Frame | 4/8/2025 | Not Ready for Inspection | BRIAN KELLY |
| Footing/Foundation/Slab | 4/9/2025 | Partial Approval | BRIAN KELLY |
| Reinforced Concrete Frame | 4/9/2025 | Partial Approval | BRIAN KELLY |
| Footing/Foundation/Slab | 4/14/2025 | Partial Approval | BRIAN KELLY |
| Reinforced Concrete Frame | 4/14/2025 | Partial Approval | BRIAN KELLY |
| Footing/Foundation/Slab | 4/30/2025 | Partial Approval | BRIAN KELLY |
| Reinforced Concrete Frame | 4/30/2025 | Partial Approval | BRIAN KELLY |
| Footing/Foundation/Slab | 5/2/2025 | Partial Approval | BRIAN KELLY |
| Reinforced Concrete Frame | 5/2/2025 | Partial Approval | BRIAN KELLY |
| Footing/Foundation/Slab | 5/7/2025 | Not Ready for Inspection | GREGORY POMISH |
| Reinforced Concrete Frame | 5/7/2025 | Not Ready for Inspection | GREGORY POMISH |
| Footing/Foundation/Slab | 5/9/2025 | Partial Approval | GREGORY POMISH |
| Reinforced Concrete Frame | 5/9/2025 | Partial Approval | GREGORY POMISH |
| Deputy Steel/Welding | 5/15/2025 | Conditional Approval | BRIAN KELLY |
| Footing/Foundation/Slab | 5/20/2025 | Partial Approval | BRIAN KELLY |
| Reinforced Concrete Frame | 5/20/2025 | Partial Approval | BRIAN KELLY |
| Wood Frame | 6/18/2025 | Partial Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2025 | Partial Approval | BRIAN KELLY |
| Wood Frame | 7/2/2025 | Partial Approval | BRIAN KELLY |
| Wood Frame | 7/17/2025 | Partial Approval | BRIAN KELLY |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2025 | Partial Approval | BRIAN KELLY |
| Light Gage Steel Frame | 7/25/2025 | Partial Approval | BRIAN KELLY |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2025 | Partial Inspection | BRIAN KELLY |
| Light Gage Steel Frame | 8/4/2025 | Partial Approval | ROBERT DAVIS |
| Deputy Wood Construction | 8/5/2025 | Conditional Approval | BRIAN KELLY |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2025 | Approved | BRIAN KELLY |
| Interior/Exterior Lathing | 8/11/2025 | Partial Inspection | BRIAN KELLY |
| Interior/Exterior Lathing | 8/13/2025 | Not Ready for Inspection | BRIAN KELLY |
| Interior/Exterior Lathing | 8/15/2025 | Approved | BRIAN KELLY |
| Special/Order Compliance | 8/27/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 9/23/2025 | Partial Inspection | BRIAN KELLY |
| Final | 9/30/2025 | Permit Finaled | BRIAN KELLY |
| Green Building Final | 9/30/2025 | Approved | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 9/30/2025 | SGSOV Approved | BRIAN KELLY |
| Smoke Detectors | 9/30/2025 | Approved | BRIAN KELLY |