6499-6501 N CAPPS AVE 91335
Certificate Information: 6499-6501 N CAPPS AVE 91335
- Application / Permit
- 23016-20000-43036
- Plan Check / Job No.
- B23VN16694
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EX ATTACHED GARAGE INTO JR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) & 65852.22 - PER WFPP
- Permit Issued
- Issued on 2/16/2024
- Issuing Office
- Current Status
- CofO Issued on 11/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2023 | HAYATO TSUCHIYA |
| Corrections Issued | 12/9/2023 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 12/12/2023 | APPLICANT |
| Applicant returned to address corrections | 1/24/2024 | OMAR GARNICA |
| Applicant returned to address corrections | 2/12/2024 | MOHAMMAD ESMAILI |
| Issued | 2/16/2024 | APPLICANT |
| CofO in Progress | 9/27/2024 | JON MCHUGH |
| Permit Finaled | 11/19/2024 | JOHN JANSON |
| CofO Issued | 11/19/2024 | JOHN JANSON |
| Permit Finaled | 11/19/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/13/2023 | GABRIELLA TORRES |
| Sewer availability | Cleared | 12/13/2023 | GABRIELLA TORRES |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2023 | GABRIELLA TORRES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/6/2024 | Corrections Issued | JON MCHUGH |
| Pre-Inspection | 3/6/2024 | Partial Approval | JON MCHUGH |
| Sewer | 3/6/2024 | Not Ready for Inspection | JON MCHUGH |
| Sewer | 3/7/2024 | Not Ready for Inspection | MORRIS JACKSON |
| Underground Mechanical | 3/7/2024 | Approved | MORRIS JACKSON |
| Footing/Foundation/Slab | 3/28/2024 | Approved | ALEXANDER HANDY |
| Deputy Wood Construction | 4/30/2024 | Conditional Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 5/6/2024 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 5/6/2024 | Approved | TROY SANDERS |
| HVAC-Rough | 5/6/2024 | Approved | TROY SANDERS |
| PLUMBING-Rough | 5/6/2024 | Approved | TROY SANDERS |
| Insulation | 5/8/2024 | Corrections Issued | JON MCHUGH |
| Insulation | 5/10/2024 | Corrections Issued | JON MCHUGH |
| Insulation | 5/14/2024 | No Access for Inspection | MORRIS JACKSON |
| Insulation | 5/16/2024 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 5/16/2024 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 5/20/2024 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 5/20/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 7/18/2024 | Not Ready for Inspection | MORRIS JACKSON |
| Final | 7/18/2024 | Corrections Issued | MORRIS JACKSON |
| Green Building Final | 7/18/2024 | Approved | MORRIS JACKSON |
| HVAC-Final | 7/18/2024 | Approved | MORRIS JACKSON |
| PLUMBING-Final | 7/18/2024 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 7/18/2024 | SGSOV Approved | MORRIS JACKSON |
| Smoke Detectors | 7/18/2024 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 7/19/2024 | Corrections Issued | JON MCHUGH |
| HVAC-Final | 7/19/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 7/19/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 7/23/2024 | Approved | JON MCHUGH |
| Final | 7/23/2024 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Final | 7/23/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 7/23/2024 | Approved | JON MCHUGH |
| Service/Power Release | 7/23/2024 | Approved | JON MCHUGH |
| Final | 9/27/2024 | OK to Issue CofO | JON MCHUGH |