1111 S FIGUEROA ST 90015

Certificate Information: 1111 S FIGUEROA ST 90015

Application / Permit
23016-20000-42684
Plan Check / Job No.
B23VN16593
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(4) Sports Arena (unlimited seating capacity)
Work Description
T.I. OF (E) ARENA: ENLARGEMENT+RELOCATION OF (E) LOCKER ROOMS (NHL VIS. TEAM+NBA VIS. TEAM), RELOCATION OF (E) SUPPORT SPACES (XRAY, WEIGHTROOM+LAUNDRY), REDUCTION OF STORAGE ROOMS, REMOVAL OF (E) CLIPPER LOCKER ROOM, WORK ALSO INCLUDES THE PERIMETER WALLS OF NHL+NBA HOME SHELL SPACE.
Permit Issued
Issued on 3/25/2025
Issuing Office
Current Status
Issued on 3/25/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/8/2023 APPLICANT
Assigned to Plan Check Engineer 12/14/2023 SEAN SHAHMIRI
Assigned to Zoning Architect 12/14/2023 SEAN SHAHMIRI
Corrections Issued 12/22/2023 SEAN SHAHMIRI
Quality Review Completed 12/29/2023 STEVEN KIM
Applicant returned to address corrections 1/31/2025 SEAN SHAHMIRI
Plan Check Approved 3/24/2025 SEAN SHAHMIRI
Issued 3/25/2025 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 1/30/2024 RYAN LY
City owned building/parcel Cleared 2/5/2024 SEAN SHAHMIRI
Specific Plan Cleared 2/21/2024 SOPHIA KIM
Green Code Cleared 2/7/2025 MICHAEL AYERS
Fire Marshal Fire Life Safety Cleared 2/21/2025 MENOA AGHAJANI
DAS Clearance Cleared 3/18/2025 Lawrence Quirante
Zoning Plan Check Cleared 3/24/2025 Lawrence Quirante

Contact Information

Architect Chung,, Steven Chen; Lic. No.: C30725 2017 MANNING AVE      LOS ANGELES, CA 90025
Contractor Pcl Construction Services Inc; Lic. No.: 474555-B       ,
Engineer Towers,, Kevin; Lic. No.: S6625 6121 IROQUOIS RD      WESTMINSTER, CA 92683

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/29/2025 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 5/29/2025 Partial Approval CHRISTOPHER BLACKWOOD
Footing/Foundation/Slab 5/29/2025 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 6/1/2025 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 6/1/2025 Partial Approval JEROME BLACKWOOD
Footing/Foundation/Slab 6/1/2025 Off-Hour Fees Due
Footing/Foundation/Slab 6/1/2025 Partial Approval JEROME BLACKWOOD
Masonry Wall/Backfill 6/4/2025 Off-Hour Fees Due
Masonry Wall/Backfill 6/4/2025 Partial Approval LUIS CCAMACHO
Reinforced Masonry Frame 6/4/2025 Partial Approval LUIS CCAMACHO
Deputy Reinf. Masonry 6/5/2025 Partial Approval PAUL BAZERKANIAN
Excavation/Setback/Form/Re-Bar 6/5/2025 Partial Approval RAFAEL CORTES
Masonry Wall/Backfill 6/5/2025 Partial Approval PAUL BAZERKANIAN
Light Gage Steel Frame 6/8/2025 Partial Approval ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 6/10/2025 Partial Approval PAUL BAZERKANIAN
Excavation/Setback/Form/Re-Bar 6/11/2025 Partial Approval PAUL BAZERKANIAN
Footing/Foundation/Slab 6/11/2025 Partial Approval PAUL BAZERKANIAN
Light Gage Steel Frame 6/11/2025 Conditional Approval DARRYL ARNOLD
Masonry Wall/Backfill 6/11/2025 Partial Approval PAUL BAZERKANIAN
Reinforced Masonry Frame 6/11/2025 Conditional Approval DARRYL ARNOLD
Drywall Nailing 6/12/2025 Partial Approval RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 6/12/2025 Partial Approval PAUL BAZERKANIAN
Masonry Wall/Backfill 6/12/2025 Partial Approval LUIS CCAMACHO
Masonry Wall/Backfill 6/12/2025 Partial Approval RONALD JIMENEZ
Reinforced Masonry Frame 6/12/2025 Off-Hour Fees Due
Drywall Nailing 6/13/2025 Partial Approval PAUL BAZERKANIAN
Excavation/Setback/Form/Re-Bar 6/13/2025 Partial Approval TIMOTHY POWELL
Drywall Nailing 6/14/2025 Off-Hour Fees Due
Drywall Nailing 6/14/2025 Partial Approval ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 6/14/2025 Off-Hour Fees Due
Light Gage Steel Frame 6/14/2025 Off-Hour Fees Due
Light Gage Steel Frame 6/14/2025 Partial Approval ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 6/15/2025 Off-Hour Fees Due
Drywall Nailing 6/16/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 6/17/2025 Approved DARRYL ARNOLD
Light Gage Steel Frame 6/17/2025 Off-Hour Fees Due
Drywall Nailing 6/18/2025 Partial Approval PAUL BAZERKANIAN
Excavation/Setback/Form/Re-Bar 6/18/2025 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 6/18/2025 Partial Approval CHRISTOPHER BLACKWOOD
Insulation 6/18/2025 Off-Hour Fees Due
Insulation 6/18/2025 Partial Approval CHRISTOPHER BLACKWOOD
Insulation 6/18/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 6/19/2025 Not Ready for Inspection JEROME BLACKWOOD
Excavation/Setback/Form/Re-Bar 6/20/2025 Partial Approval JEROME BLACKWOOD
Excavation/Setback/Form/Re-Bar 6/21/2025 Partial Approval MARTIN TAVITIAN
Drywall Nailing 6/22/2025 Conditional Approval DARRYL ARNOLD
Drywall Nailing 6/24/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 6/24/2025 Partial Approval RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 6/24/2025 Not Ready for Inspection PAUL BAZERKANIAN
Drywall Nailing 6/26/2025 Partial Approval ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 6/27/2025 Partial Approval PAUL BAZERKANIAN
Footing/Foundation/Slab 6/27/2025 Partial Approval MARTIN TAVITIAN
Drywall Nailing 6/30/2025 Partial Approval PAUL BAZERKANIAN
Final 7/1/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Final 7/1/2025 Off-Hour Fees Due
Green Building Final 7/1/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Green Building Final 7/1/2025 Off-Hour Fees Due
Light Gage Steel Frame 7/1/2025 Partial Approval CHRISTOPHER BLACKWOOD
METHANE-Final 7/1/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
METHANE-Final 7/1/2025 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 7/1/2025 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 7/1/2025 SGSOV Not Ready CHRISTOPHER BLACKWOOD
Smoke Detectors 7/1/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Smoke Detectors 7/1/2025 Off-Hour Fees Due
Insulation 7/3/2025 Partial Approval ALFREDO LOPEZ
Insulation 7/7/2025 Partial Approval MARTIN TAVITIAN
Masonry Wall/Backfill 7/7/2025 Partial Approval PAUL BAZERKANIAN
Light Gage Steel Frame 7/8/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 7/9/2025 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 7/10/2025 Partial Approval JEROME BLACKWOOD
Insulation 7/10/2025 Partial Approval JEROME BLACKWOOD
Drywall Nailing 7/11/2025 Partial Approval RONALD JIMENEZ
Insulation 7/11/2025 Partial Approval RONALD JIMENEZ
Drywall Nailing 7/12/2025 Partial Approval ALFREDO LOPEZ
Insulation 7/12/2025 Partial Approval ALFREDO LOPEZ
Drywall Nailing 7/14/2025 Conditional Approval DARRYL ARNOLD
Drywall Nailing 7/15/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Light Gage Steel Frame 7/15/2025 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 7/17/2025 Partial Approval ALFREDO LOPEZ
Light Gage Steel Frame 7/17/2025 Partial Approval ALFREDO LOPEZ
Drywall Nailing 7/18/2025 Off-Hour Fees Due
Drywall Nailing 7/18/2025 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 7/18/2025 Partial Approval JEROME BLACKWOOD
Insulation 7/18/2025 Not Ready for Inspection CHRISTOPHER BLACKWOOD
Insulation 7/18/2025 Off-Hour Fees Due
Light Gage Steel Frame 7/18/2025 Off-Hour Fees Due
Light Gage Steel Frame 7/18/2025 Partial Approval CHRISTOPHER BLACKWOOD
Light Gage Steel Frame 7/18/2025 Partial Approval JEROME BLACKWOOD
Drywall Nailing 7/19/2025 Off-Hour Fees Due
Light Gage Steel Frame 7/19/2025 Off-Hour Fees Due
Drywall Nailing 7/21/2025 Partial Approval PAUL BAZERKANIAN
Light Gage Steel Frame 7/21/2025 Off-Hour Fees Due
Light Gage Steel Frame 7/21/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 7/23/2025 Partial Approval LUIS CCAMACHO
Insulation 7/23/2025 Partial Approval LUIS CCAMACHO
Drywall Nailing 7/25/2025 Off-Hour Fees Due
Drywall Nailing 7/25/2025 Partial Approval CHRISTOPHER BLACKWOOD
Excavation/Setback/Form/Re-Bar 7/25/2025 Partial Approval PAUL BAZERKANIAN
Insulation 7/25/2025 Partial Approval CHRISTOPHER BLACKWOOD
Light Gage Steel Frame 7/25/2025 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 7/29/2025 Partial Approval ADAM BURGESS
Insulation 7/29/2025 Not Ready for Inspection ADAM BURGESS
Drywall Nailing 7/31/2025 Approved DARRYL ARNOLD
Light Gage Steel Frame 7/31/2025 Approved DARRYL ARNOLD
Drywall Nailing 8/1/2025 Partial Approval ALFREDO LOPEZ
Insulation 8/1/2025 Partial Approval ALFREDO LOPEZ
Drywall Nailing 8/4/2025 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 8/5/2025 Partial Approval TIMOTHY POWELL
Insulation 8/5/2025 Partial Approval TIMOTHY POWELL
Drywall Nailing 8/6/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 8/8/2025 Partial Approval CHRISTOPHER BLACKWOOD
Insulation 8/8/2025 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 8/12/2025 Partial Approval MARTIN TAVITIAN
Light Gage Steel Frame 8/12/2025 Partial Approval MARTIN TAVITIAN
Drywall Nailing 8/13/2025 Partial Approval JEROME BLACKWOOD
Pre-Inspection 8/13/2025 Approved JOEY BUCHANAN
Drywall Nailing 8/14/2025 Partial Approval JOEY BUCHANAN
Insulation 8/14/2025 Partial Approval CHRISTOPHER BLACKWOOD
Light Gage Steel Frame 8/14/2025 Partial Approval CHRISTOPHER BLACKWOOD
T-Bar Ceiling 8/14/2025 Partial Approval JOEY BUCHANAN
Drywall Nailing 8/15/2025 Partial Approval ALFREDO LOPEZ
Drywall Nailing 8/16/2025 Partial Approval JEROME BLACKWOOD
Drywall Nailing 8/19/2025 Partial Approval ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 8/19/2025 Partial Approval ALFREDO LOPEZ
Drywall Nailing 8/20/2025 Off-Hour Fees Due
Drywall Nailing 8/20/2025 Partial Approval PAUL BAZERKANIAN
T-Bar Ceiling 8/20/2025 Off-Hour Fees Due
T-Bar Ceiling 8/20/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 8/21/2025 Partial Approval PAUL BAZERKANIAN
Insulation 8/21/2025 Not Ready for Inspection MARTIN TAVITIAN
Light Gage Steel Frame 8/21/2025 Partial Approval PAUL BAZERKANIAN
T-Bar Ceiling 8/21/2025 Partial Approval MARTIN TAVITIAN
T-Bar Ceiling 8/21/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 8/22/2025 Approved DARRYL ARNOLD
Drywall Nailing 8/22/2025 Off-Hour Fees Due
T-Bar Ceiling 8/22/2025 Approved DARRYL ARNOLD
T-Bar Ceiling 8/22/2025 Off-Hour Fees Due
Drywall Nailing 8/23/2025 Partial Approval CHRISTOPHER BLACKWOOD
Light Gage Steel Frame 8/23/2025 Partial Approval CHRISTOPHER BLACKWOOD
Drywall Nailing 8/24/2025 Partial Approval PAUL BAZERKANIAN
Light Gage Steel Frame 8/24/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 8/25/2025 Partial Inspection JEROME BLACKWOOD
Light Gage Steel Frame 8/25/2025 Partial Inspection JEROME BLACKWOOD
T-Bar Ceiling 8/25/2025 Partial Inspection JEROME BLACKWOOD
T-Bar Ceiling 8/26/2025 Not Ready for Inspection PAUL BAZERKANIAN
Drywall Nailing 8/27/2025 Partial Approval ALFREDO LOPEZ
Pre-Inspection 8/27/2025 Partial Approval PAUL BAZERKANIAN
T-Bar Ceiling 8/27/2025 Partial Approval ALFREDO LOPEZ
Drywall Nailing 8/29/2025 Partial Approval CHRISTOPHER BLACKWOOD
Insulation 8/29/2025 Partial Approval CHRISTOPHER BLACKWOOD
Light Gage Steel Frame 8/30/2025 Conditional Approval ADAM BURGESS
Light Gage Steel Frame 8/30/2025 Off-Hour Fees Due
Drywall Nailing 9/2/2025 Partial Approval PAUL BAZERKANIAN
Drywall Nailing 9/6/2025 Approved RONALD JIMENEZ
Light Gage Steel Frame 9/6/2025 Approved RONALD JIMENEZ
Drywall Nailing 9/8/2025 Approved ALFREDO LOPEZ
Final 1/14/2026 Partial Approval PAUL BAZERKANIAN
Green Building Final 1/14/2026 Approved PAUL BAZERKANIAN
METHANE-Final 1/14/2026 Approved PAUL BAZERKANIAN
SGSOV-Seismic Gas S/O Valve 1/14/2026 SGSOV Approved PAUL BAZERKANIAN
Smoke Detectors 1/14/2026 Approved PAUL BAZERKANIAN