1111 S FIGUEROA ST 90015

Certificate Information: 1111 S FIGUEROA ST 90015

Application / Permit
23016-20000-42678
Plan Check / Job No.
B23VN16587
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(4) Sports Arena (unlimited seating capacity)
Work Description
ePlan INTERIOR TENANT IMPROVEMENT / ALTERATION OF EXISTING ARENA BUILDING. THE PROJECT SCOPE INCLUDES A NEW INTERIOR CITY VIEW TERRACE CLUB (CVT) WHICH INCLUDES THE REMOVAL OF UPPER SEATING BOWL SEATS(REMOVAL OF 327 SEATS FROM SECTIONS #325, 326, 327,328) FOR THE NEW CLUB (2,830SF) WITH 128 TICKETED SEATS(FIXED SEATS AND DRINK RAILS). THE NEW PROJECT CREATES A NET REDUCTION OF 199 OCCUPANTS ON THE UPPER SEATING BOWL. THE EXTERIOR RENOVATION INCLUDES THE REPAIR OF TOPPING SLAB ON EXISTING EXTERIOR TERRACE (9,600SF) WITH THE ADDITION OF A NEW EXTERIOR PERMANENT BAR (520SF) AND REPLACEMENT OF CURTAINWALL. NO ADDED STORIES, NO CHANGE OF OCCUPANCY TYPE, REDUCTION OF 199 OCCUPANTS IN OVERALL BUILDING. ***SEE COMMENTS***
Permit Issued
Issued on 6/5/2024
Issuing Office
Current Status
Permit Finaled on 11/25/2024

Permit Application Status History

Submitted 12/4/2023 APPLICANT
Assigned to Zoning Architect 12/7/2023 MICHAEL LOPEZ
Assigned to Plan Check Engineer 12/7/2023 JOHNNY WU
Corrections Issued 12/21/2023 MICHAEL LOPEZ
Quality Review Completed 12/26/2023 PRANITA SHAH
Applicant returned to address corrections 2/5/2024 MICHAEL LOPEZ
Applicant returned to address corrections 2/21/2024 MICHAEL LOPEZ
Applicant returned to address corrections 5/2/2024 JOHNNY WU
Applicant returned to address corrections 5/3/2024 JOHNNY WU
Applicant returned to address corrections 5/8/2024 JOHNNY WU
Applicant returned to address corrections 6/4/2024 JOHNNY WU
Plan Check Approved 6/5/2024 JOHNNY WU
Issued 6/5/2024 APPLICANT
Permit Finaled 11/20/2024 PAUL BAZERKANIAN

Permit Application Clearance Information

CPC Cleared 1/30/2024 RYAN LY
CPC Cleared 1/30/2024 RYAN LY
CPC Cleared 1/30/2024 RYAN LY
Specific Plan Cleared 1/30/2024 SOPHIA KIM
ZA Case Cleared 1/30/2024 RYAN LY
City owned building/parcel Cleared 1/31/2024 MICHAEL LOPEZ
Food Service Establishment Cleared 3/15/2024 RAMESHBHAIR PATEL
Green Code Cleared 4/23/2024 MICHAEL AYERS
Eng Process Fee Ord 176,300 Cleared 4/29/2024 TREVOR QUAN
Sewer availability Cleared 4/29/2024 TREVOR QUAN
Food establishment approval Cleared 5/6/2024 LACDHS APPROVED
Fire Marshal Fire Life Safety Cleared 5/28/2024 MENOA AGHAJANI
DAS Clearance Cleared 6/4/2024 Lawrence Quirante
Zoning Plan Check Cleared 6/4/2024 Lawrence Quirante

Contact Information

Architect Chung,, Steven Chen; Lic. No.: NA30725       ,
Contractor Pcl Construction Services Inc; Lic. No.: 474555-B       ,
Engineer Towers,, Kevin; Lic. No.: NA6625       ,

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 6/12/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 6/18/2024 Off-Hour Fees Due
Pre-Inspection 6/18/2024 Conditional Approval DARRYL ARNOLD
Pre-Inspection 6/18/2024 Off-Hour Fees Due
T-Bar Ceiling 6/18/2024 Conditional Approval DARRYL ARNOLD
T-Bar Ceiling 6/18/2024 Off-Hour Fees Due
Drywall Nailing 6/20/2024 Conditional Approval DARRYL ARNOLD
Final 6/20/2024 Off-Hour Fees Due
Green Building Final 6/20/2024 Off-Hour Fees Due
Light Gage Steel Frame 6/20/2024 Conditional Approval DARRYL ARNOLD
Light Gage Steel Frame 6/20/2024 Off-Hour Fees Due
SGSOV-Seismic Gas S/O Valve 6/20/2024 Off-Hour Fees Due
Smoke Detectors 6/20/2024 Off-Hour Fees Due
Drywall Nailing 6/21/2024 Partial Approval MARTIN TAVITIAN
Light Gage Steel Frame 6/21/2024 Partial Approval MARTIN TAVITIAN
Drywall Nailing 6/22/2024 Partial Approval ALFREDO LOPEZ
Drywall Nailing 6/25/2024 Partial Approval MARTIN TAVITIAN
Light Gage Steel Frame 6/25/2024 Partial Approval MARTIN TAVITIAN
Drywall Nailing 6/26/2024 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 7/10/2024 Partial Approval LUIS CCAMACHO
Excavation/Setback/Form/Re-Bar 7/16/2024 Partial Approval ALFREDO LOPEZ
Deputy Drilled-In Anchors 7/24/2024 Approved JEROME BLACKWOOD
Deputy Reinf. Concrete 7/24/2024 Approved JEROME BLACKWOOD
Deputy Steel/Welding 7/24/2024 Approved JEROME BLACKWOOD
Excavation/Setback/Form/Re-Bar 7/24/2024 Partial Approval ALFREDO LOPEZ
Excavation/Setback/Form/Re-Bar 7/25/2024 Approved DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 8/7/2024 Partial Approval RAFAEL CORTES
Deputy Drilled-In Anchors 8/8/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 8/8/2024 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 8/8/2024 Partial Approval RAMAZANALI ALMASI
Light Gage Steel Frame 8/10/2024 Approved DARRYL ARNOLD
Structural Steel Frame 8/10/2024 Approved DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 8/12/2024 Partial Approval JEROME BLACKWOOD
Deputy Drilled-In Anchors 8/15/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Fireproofing 8/15/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 8/15/2024 Conditional Approval MICHAEL ROSENBERG
Drywall Nailing 8/15/2024 Partial Approval RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 8/15/2024 Corrections Issued RONALD JIMENEZ
Light Gage Steel Frame 8/15/2024 Partial Approval RONALD JIMENEZ
Drywall Nailing 8/16/2024 Off-Hour Fees Due
Drywall Nailing 8/16/2024 Partial Approval ALFREDO LOPEZ
Light Gage Steel Frame 8/16/2024 Off-Hour Fees Due
Light Gage Steel Frame 8/16/2024 Partial Approval ALFREDO LOPEZ
Drywall Nailing 8/17/2024 Approved DARRYL ARNOLD
Drywall Nailing 8/17/2024 Conditional Approval DARRYL ARNOLD
Drywall Nailing 8/17/2024 Off-Hour Fees Due
Drywall Nailing 8/18/2024 Partial Approval JEROME BLACKWOOD
Drywall Nailing 8/24/2024 Partial Approval RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 8/24/2024 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 8/26/2024 Partial Approval ALFREDO LOPEZ
Light Gage Steel Frame 8/26/2024 Partial Approval ALFREDO LOPEZ
Drywall Nailing 8/30/2024 Partial Approval JEROME BLACKWOOD
Drywall Nailing 9/3/2024 Partial Approval ALFREDO LOPEZ
Light Gage Steel Frame 9/3/2024 Partial Approval ALFREDO LOPEZ
T-Bar Ceiling 9/3/2024 Partial Approval ALFREDO LOPEZ
Drywall Nailing 9/4/2024 Partial Approval LARRY ARNICK
Insulation 9/4/2024 Partial Approval LARRY ARNICK
Drywall Nailing 9/6/2024 Approved RONALD JIMENEZ
Light Gage Steel Frame 9/6/2024 Not Ready for Inspection RONALD JIMENEZ
Light Gage Steel Frame 9/12/2024 Partial Approval MARTIN TAVITIAN
Wood Frame 9/12/2024 Partial Approval MARTIN TAVITIAN
Drywall Nailing 9/14/2024 Partial Approval TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 9/18/2024 Partial Approval RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 9/21/2024 Approved RONALD JIMENEZ
Footing/Foundation/Slab 9/23/2024 Partial Approval TIMOTHY POWELL
Deputy Steel/Welding 10/1/2024 Partial Approval JEROME BLACKWOOD
Pre-Inspection 10/1/2024 Not Ready for Inspection JEROME BLACKWOOD
Final 10/16/2024 Partial Inspection ALFREDO LOPEZ
Green Building Final 10/16/2024 Not Ready for Inspection ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 10/16/2024 SGSOV Not Ready ALFREDO LOPEZ
Smoke Detectors 10/16/2024 Not Ready for Inspection ALFREDO LOPEZ
Final 10/18/2024 Partial Inspection TIMOTHY POWELL
Green Building Final 10/18/2024 Not Ready for Inspection TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 10/18/2024 SGSOV Not Ready TIMOTHY POWELL
Smoke Detectors 10/18/2024 Not Ready for Inspection TIMOTHY POWELL
Final 10/31/2024 Not Ready for Inspection PAUL BAZERKANIAN
SGSOV-Seismic Gas S/O Valve 10/31/2024 SGSOV Not Ready PAUL BAZERKANIAN
Final 11/20/2024 Permit Finaled PAUL BAZERKANIAN
Green Building Final 11/20/2024 Approved PAUL BAZERKANIAN
SGSOV-Seismic Gas S/O Valve 11/20/2024 SGSOV Approved PAUL BAZERKANIAN
Smoke Detectors 11/20/2024 Approved PAUL BAZERKANIAN