702 E 41ST PL 90011

Certificate Information: 702 E 41ST PL 90011

Application / Permit
23016-20000-42594
Plan Check / Job No.
B23VN16564
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remodel for (E) SFD **"COMPLY WITH DEPARTMENT ORDER effective date 11/07/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 4/18/2024
Issuing Office
Current Status
Permit Finaled on 9/17/2024

Permit Application Status History

Submitted 12/4/2023 APPLICANT
Assigned to Plan Check Engineer 12/6/2023 NEHEMIAS RAMOS
Corrections Issued 12/7/2023 NEHEMIAS RAMOS
Plan Check Approved 1/18/2024 ZAW HAN
Issued 4/18/2024 APPLICANT
Permit Finaled 9/17/2024 DANIEL GONZALEZ

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Lajoma Construction Inc; Lic. No.: 864461-B       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
Rough-Elec/Plmb/HVAC 6/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
Rough-Elec/Plmb/HVAC 6/12/2024 Not Ready for Inspection ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 6/14/2024 Not Ready for Inspection DANIEL GUEVARA
Floor/Roof Diaphrgm/Shear Wall 6/14/2024 Approved DANIEL GUEVARA
Gas Test 6/14/2024 Approved DANIEL GUEVARA
Interior/Exterior Lathing 6/14/2024 Partial Approval DANIEL GUEVARA
Rough-Elec/Plmb/HVAC 6/14/2024 Corrections Issued DANIEL GUEVARA
BUILDING-Rough-Frame 6/20/2024 Approved DANIEL GONZALEZ
HVAC-Rough 6/20/2024 Conditional Approval DANIEL GONZALEZ
BUILDING-Rough-Frame 6/21/2024 Not Ready for Inspection DANIEL GONZALEZ
Insulation 6/21/2024 Not Ready for Inspection DANIEL GONZALEZ
Insulation 6/24/2024 Approved DANIEL GONZALEZ
Drywall Nailing 7/1/2024 Approved DANIEL GONZALEZ
ELECTRICAL-Final 9/9/2024 Approved DANIEL GONZALEZ
Final 9/9/2024 Not Ready for Inspection DANIEL GONZALEZ
Gas Test 9/9/2024 Approved DANIEL GONZALEZ
HVAC-Final 9/9/2024 Corrections Issued DANIEL GONZALEZ
PLUMBING-Final 9/9/2024 Approved DANIEL GONZALEZ
SGSOV-Seismic Gas S/O Valve 9/9/2024 SGSOV Approved DANIEL GONZALEZ
Service/Power Release 9/9/2024 Approved DANIEL GONZALEZ
Smoke Detectors 9/9/2024 Approved DANIEL GONZALEZ
Final 9/17/2024 Permit Finaled DANIEL GONZALEZ