19124 W HARTLAND ST 91335

Certificate Information: 19124 W HARTLAND ST 91335

Application / Permit
23016-20000-41841
Plan Check / Job No.
B23VN16248
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE INTO (N) 365 SF ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d). ALL WORK PER WFPP.
Permit Issued
Issued on 12/7/2023
Issuing Office
Valley
Current Status
CofO Issued on 7/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/28/2023 APPLICANT
Assigned to Plan Check Engineer 12/1/2023 HAYATO TSUCHIYA
Corrections Issued 12/2/2023 HAYATO TSUCHIYA
Building Plans Picked Up 12/5/2023 APPLICANT
Issued 12/7/2023 APPLICANT
CofO in Progress 6/11/2024 KRISTEN BEVERIDGE
Permit Finaled 7/23/2024 JOHN JANSON
CofO Issued 7/23/2024 JOHN JANSON
Permit Finaled 7/23/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/4/2023 EDGAR ALCARAZ
Sewer availability Cleared 12/4/2023 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/5/2023 EDGAR ALCARAZ
ZI Cleared 12/5/2023 STEVEN WECHSLER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/8/2024 Partial Approval JEFFREY BULL
Deputy Drilled-In Anchors 1/10/2024 Approved JEFFREY BULL
Footing/Foundation/Slab 1/10/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 2/6/2024 Not Ready for Inspection JEFFREY BULL
Green Building Rough 2/6/2024 Approved JEFFREY BULL
Insulation 2/6/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 2/6/2024 Approved JEFFREY BULL
Shower Pan 2/6/2024 Approved JEFFREY BULL
Drywall Nailing 2/15/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 3/22/2024 SGSOV Approved KRISTEN CAUSEY
Smoke Detectors 3/22/2024 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 6/6/2024 Not Ready for Inspection KRISTEN CAUSEY
Final 6/6/2024 Not Ready for Inspection KRISTEN CAUSEY
Green Building Final 6/6/2024 Not Ready for Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 6/11/2024 Approved KRISTEN CAUSEY
Final 6/11/2024 OK to Issue CofO KRISTEN CAUSEY
Green Building Final 6/11/2024 Approved KRISTEN CAUSEY