22749-22751 W MIRANDA ST 91367
Certificate Information: 22749-22751 W MIRANDA ST 91367
- Application / Permit
- 23016-20000-41374
- Plan Check / Job No.
- B23VN16154
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Convert an existing attached 2-car garage to a JADU PER STATE LAW
- Permit Issued
- Issued on 1/17/2024
- Issuing Office
- Current Status
- CofO Issued on 1/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2023 | NEHEMIAS RAMOS |
| Corrections Issued | 11/30/2023 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 12/20/2023 | WEIJIAN HUANG |
| Applicant returned to address corrections | 12/28/2023 | KHUONG TRUONG |
| Applicant returned to address corrections | 1/8/2024 | KHUONG TRUONG |
| Plan Check Approved | 1/9/2024 | KHUONG TRUONG |
| Plan Check Approved | 1/17/2024 | KHUONG TRUONG |
| Issued | 1/17/2024 | APPLICANT |
| CofO in Progress | 4/24/2024 | TROY SANDERS |
| No Progress | 1/9/2025 | TROY SANDERS |
| CofO in Progress | 1/9/2025 | TROY SANDERS |
| Permit Finaled | 1/15/2025 | JOHN JANSON |
| CofO Issued | 1/15/2025 | JOHN JANSON |
| Permit Finaled | 1/15/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/2/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 12/2/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 12/4/2023 | COLIN LOREDO |
| Grading Pre-Inspection | Cleared | 12/19/2023 | MICHAEL TEMPLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mezey,, Steven William; Lic. No.: NA2665 | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/19/2024 | Approved | TROY SANDERS |
| Green Building Rough | 2/6/2024 | Not Ready for Inspection | TROY SANDERS |
| Wood Frame | 2/6/2024 | Approved | TROY SANDERS |
| Insulation | 2/13/2024 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 3/6/2024 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 3/12/2024 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 3/26/2024 | Approved | GEVORK IPCHYAN |
| Final | 4/16/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Final | 4/16/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Rough | 4/16/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/16/2024 | SGSOV Not Ready | GEVORK IPCHYAN |
| Smoke Detectors | 4/16/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Wood Frame | 4/16/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Final | 4/23/2024 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 4/23/2024 | Approved | TROY SANDERS |
| Green Building Rough | 4/23/2024 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 4/23/2024 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 4/23/2024 | Approved | TROY SANDERS |
| Wood Frame | 4/23/2024 | Approved | TROY SANDERS |
| Special/Order Compliance | 1/9/2025 | Corrections Issued | TROY SANDERS |