5071 W EDGEWOOD PL 90019
Certificate Information: 5071 W EDGEWOOD PL 90019
- Application / Permit
- 23016-20000-41345
- Plan Check / Job No.
- B23VN16128
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 5/30/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 11/29/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 12/1/2023 | APPLICANT |
| Issued | 5/30/2024 | APPLICANT |
| CofO in Progress | 10/30/2024 | JOSE MACIAS |
| CofO Issued | 11/4/2024 | DEROLD HAUFF |
| Permit Finaled | 11/4/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/2/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 5/2/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2024 | DAVID LOPEZ |
| Construction near power lines | Cleared | 5/21/2024 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/17/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Rough | 6/17/2024 | Approved | AMIR NAZARIAN |
| Footing/Foundation/Slab | 6/27/2024 | Corrections Issued | RONNIE MINDANAO |
| Deputy Drilled-In Anchors | 7/16/2024 | Conditional Approval | RONNIE MINDANAO |
| Footing/Foundation/Slab | 7/16/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Footing/Foundation/Slab | 7/17/2024 | No Access for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 8/12/2024 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 8/12/2024 | Corrections Issued | RONNIE MINDANAO |
| Gas Test | 8/12/2024 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 8/12/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| PLUMBING-Rough | 8/12/2024 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Rough | 8/20/2024 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 8/20/2024 | Partial Approval | RONNIE MINDANAO |
| HVAC-Rough | 8/20/2024 | Approved | RONNIE MINDANAO |
| Insulation | 8/20/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Wood Frame | 8/20/2024 | Corrections Issued | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 8/30/2024 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 8/30/2024 | Approved | ENRIQUE MIRELES |
| Insulation | 8/30/2024 | Approved | ENRIQUE MIRELES |
| METHANE-Rough | 8/30/2024 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 9/6/2024 | Approved | RONNIE MINDANAO |
| Final | 9/6/2024 | Corrections Issued | RONNIE MINDANAO |
| Shower Pan | 9/6/2024 | Corrections Issued | RONNIE MINDANAO |
| Shower Pan | 9/13/2024 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 9/16/2024 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 10/11/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 10/11/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 10/11/2024 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 10/11/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Final | 10/11/2024 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 10/11/2024 | SGSOV Approved | JOAQUIN GREENOUGH |
| Smoke Detectors | 10/11/2024 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 10/17/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 10/17/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Final | 10/17/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Final | 10/25/2024 | Approved | JOSE MACIAS |
| Final | 10/25/2024 | OK to Issue CofO | JOSE MACIAS |
| HVAC-Final | 10/25/2024 | Approved | JOSE MACIAS |
| Service/Power Release | 10/31/2024 | Approved | JOSE MACIAS |