564 N LUCERNE BLVD 90004

Certificate Information: 564 N LUCERNE BLVD 90004

Application / Permit
23016-20000-41337
Plan Check / Job No.
B23VN16122
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
CONVERT 18'x 9' PORTION OF (E) DETACHED GARAGE TO REC ROOM (162 s.f) AND 3'x18' (54 s.f) REMAINS AS NON-HABITABLE SPACE. SEE COMMENTS.
Permit Issued
Issued on 1/5/2024
Issuing Office
Metro
Current Status
CofO Issued on 12/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2023 APPLICANT
Assigned to Plan Check Engineer 11/30/2023 JEROME MAGAT PALMA
Corrections Issued 12/2/2023 JEROME MAGAT PALMA
Building Plans Picked Up 12/4/2023 APPLICANT
Plan Check Approved 12/12/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 12/12/2023 MIROOSH KHACHATOORIAN
Issued 1/5/2024 APPLICANT
CofO in Progress 11/24/2024 JEFFREY MEAD
Permit Finaled 12/3/2024 DEROLD HAUFF
CofO Issued 12/3/2024 DEROLD HAUFF
Permit Finaled 12/3/2024 DEROLD HAUFF

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Truebuilt Construction Inc; Lic. No.: 1052087-B 950 E KATELLA AVE STE 5      ORANGE, CA 92867
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/20/2024 Corrections Issued JEFFREY MEAD
Footing/Foundation/Slab 5/22/2024 Approved JEFFREY MEAD
ELECTRICAL-Rough 6/4/2024 Approved JEFFREY MEAD
PLUMBING-Rough 6/4/2024 Approved JEFFREY MEAD
HVAC-Rough 6/10/2024 Approved JEFFREY MEAD
PLUMBING-Rough 6/10/2024 Approved JEFFREY MEAD
BUILDING-Rough-Frame 6/14/2024 Partial Approval JEFFREY MEAD
Green Building Rough 6/14/2024 Approved JEFFREY MEAD
Interior/Exterior Lathing 6/14/2024 Not Ready for Inspection JEFFREY MEAD
METHANE-Rough 6/14/2024 Approved JEFFREY MEAD
Special/Order Compliance 6/17/2024 Not Ready for Inspection AMIR NAZARIAN
BUILDING-Rough-Frame 6/18/2024 Approved JEFFREY MEAD
Interior/Exterior Lathing 6/18/2024 Not Ready for Inspection JEFFREY MEAD
Insulation 6/24/2024 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 6/24/2024 Approved JOSEPH MCGARRY
Drywall Nailing 7/1/2024 Approved JEFFREY MEAD
Special/Order Compliance 8/7/2024 Approved JEFFREY MEAD
HVAC-Final 10/4/2024 Corrections Issued ENRIQUE MIRELES
Service/Power Release 10/4/2024 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 11/20/2024 SGSOV Not Ready JEFFREY MEAD
Final 11/21/2024 Not Ready for Inspection JEFFREY MEAD
HVAC-Final 11/21/2024 Approved JEFFREY MEAD
PLUMBING-Final 11/21/2024 Approved JEFFREY MEAD
Final 11/22/2024 OK to Issue CofO JEFFREY MEAD
Green Building Final 11/22/2024 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 11/22/2024 SGSOV Not Required JEFFREY MEAD
Smoke Detectors 11/22/2024 Approved JEFFREY MEAD