Work Description
Tenant Improvement of existing retail space: Removal and relocation of interior partition walls and new storage racks with 8' max height
Permit Issued
Issued on 5/7/2024
Issuing Office
San Pedro
Current Status
Permit Finaled on 8/2/2024

Permit Application Status History

Submitted 11/22/2023 APPLICANT
Assigned to Plan Check Engineer 11/30/2023 VAHAN JIVALAGIAN
Assigned to Zoning Architect 12/1/2023 VAHAN JIVALAGIAN
Corrections Issued 12/3/2023 VAHAN JIVALAGIAN
Quality Review Completed 12/4/2023 OMID HEDAYAT
Building Plans Picked Up 12/5/2023 APPLICANT
Disabled Access Plans Picked Up 12/8/2023 APPLICANT
Green Plans Picked Up 12/8/2023 APPLICANT
Plan Check Approved 3/13/2024 VAHAN JIVALAGIAN
Issued 5/7/2024 APPLICANT
Permit Finaled 7/24/2024 FARHAD DADBIN

Permit Application Clearance Information

"Q" conditions Cleared 12/6/2023 NELSON RODRIGUEZ
Coastal Zone Cleared 12/6/2023 NELSON RODRIGUEZ
Miscellaneous Cleared 12/6/2023 NELSON RODRIGUEZ
ZI Cleared 12/6/2023 NELSON RODRIGUEZ
ZI Cleared 12/6/2023 NELSON RODRIGUEZ
Green Code Cleared 1/16/2024 MICHAEL AYERS
DAS Clearance Cleared 3/7/2024 OLLIE CARTER
Zoning Plan Check Cleared 3/13/2024 VAHAN JIVALAGIAN

Contact Information

Architect Lutsch,, Michael H; Lic. No.: C29631 977 PALMER ROAD      COLUMBUS, OH 43212
Contractor J D Commercial Builders Inc; Lic. No.: 715406-B P O BOX 6479      BEND, OR 97708
Engineer Burnam,, Nicholas Stiver; Lic. No.: C85830 365 E QUMIBY      BEND, OR 97701

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 5/21/2024 Partial Approval FARHAD DADBIN
Deputy Drilled-In Anchors 5/24/2024 Conditional Approval FARHAD DADBIN
Drywall Nailing 5/28/2024 Partial Approval FARHAD DADBIN
Excavation/Setback/Form/Re-Bar 5/28/2024 Partial Approval FARHAD DADBIN
Light Gage Steel Frame 5/28/2024 Partial Approval FARHAD DADBIN
Deputy Reinf. Concrete 5/29/2024 Conditional Approval FARHAD DADBIN
Light Gage Steel Frame 6/4/2024 Conditional Approval FARHAD DADBIN
Light Gage Steel Frame 6/10/2024 Partial Approval FARHAD DADBIN
Green Building Rough 6/21/2024 No Access for Inspection GRANT WOODS
T-Bar Ceiling 6/21/2024 No Access for Inspection GRANT WOODS
T-Bar Ceiling 7/12/2024 Approved FARHAD DADBIN
Final 7/18/2024 Not Ready for Inspection FARHAD DADBIN
Green Building Final 7/18/2024 Approved FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 7/18/2024 SGSOV Approved FARHAD DADBIN
Smoke Detectors 7/18/2024 Not Ready for Inspection FARHAD DADBIN
Smoke Detectors 7/22/2024 Not Ready for Inspection FARHAD DADBIN
Final 7/24/2024 Permit Finaled FARHAD DADBIN
Smoke Detectors 7/24/2024 Approved FARHAD DADBIN