11348-11350 N CLYBOURN AVE 91342
Certificate Information: 11348-11350 N CLYBOURN AVE 91342
- Application / Permit
- 23016-20000-40872
- Plan Check / Job No.
- B23VN15919
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO JADU PER GCS 65852.2(e)(1)(A) AND 65852.22
- Permit Issued
- Issued on 8/5/2024
- Issuing Office
- Current Status
- CofO Issued on 1/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2023 | ISIS ARGUETA |
| Corrections Issued | 11/25/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 3/11/2024 | ISIS ARGUETA |
| Applicant returned to address corrections | 6/6/2024 | ISIS ARGUETA |
| Applicant returned to address corrections | 7/19/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 7/31/2024 | ALEC MOUSAKHANIAN |
| Issued | 8/5/2024 | APPLICANT |
| CofO in Progress | 1/23/2025 | MICHEL ABAJAN |
| Permit Finaled | 1/28/2025 | RUBEN SALAS |
| CofO Issued | 1/28/2025 | RUBEN SALAS |
| Permit Finaled | 1/28/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/9/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 3/9/2024 | EDGAR ALCARAZ |
| Grading Pre-Inspection | Cleared | 3/16/2024 | CHARLES POWELL |
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2024 | EDGAR ALCARAZ |
| Specific Plan | Cleared | 4/10/2024 | JOSHUA ORDONEZ |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: NA23963 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/29/2024 | Partial Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 9/5/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 9/5/2024 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 9/10/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 9/10/2024 | Approved | MICHEL ABAJAN |
| FLOOD-Proofing Certificate | 9/10/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 9/10/2024 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 9/10/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 9/10/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2024 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 9/12/2024 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 9/16/2024 | Approved | MICHEL ABAJAN |
| Gas Test | 9/16/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 9/16/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 10/4/2024 | Approved | MICHEL ABAJAN |
| Final | 10/4/2024 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 10/4/2024 | Approved | MICHEL ABAJAN |
| HVAC-Final | 10/4/2024 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 10/4/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 10/4/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 10/4/2024 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 10/4/2024 | Approved | MICHEL ABAJAN |
| Final | 12/10/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 1/22/2025 | OK to Issue CofO | MICHEL ABAJAN |