5254-5256 N ALLOTT AVE 91401
Certificate Information: 5254-5256 N ALLOTT AVE 91401
- Application / Permit
- 23016-20000-39800
- Plan Check / Job No.
- B23VN15593
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 27'11" X 19' IRREGULARLY SHAPED ATTACHED GARAGE (318 SF) AND (E) 11'11" X 10'9" IRREGULARLY SHAPED PORTION OF SFD (84 SF) TO (N) JUNIOR ACCESSORY DWELLING UNIT (403 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22. WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 11/21/2023
- Issuing Office
- Current Status
- CofO Issued on 6/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 11/17/2023 | JEROME MAGAT PALMA |
| Issued | 11/21/2023 | APPLICANT |
| Building Plans Picked Up | 11/21/2023 | APPLICANT |
| CofO in Progress | 6/4/2024 | JUAN VALENZUELA |
| CofO Issued | 6/4/2024 | RUBEN SALAS |
| Permit Finaled | 6/4/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 11/17/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/29/2024 | Conditional Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 1/29/2024 | Approved | MISAEL ESPARZA |
| Underground Mechanical | 1/29/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 1/31/2024 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/13/2024 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 2/13/2024 | Approved | JUAN VALENZUELA |
| Green Building Rough | 2/13/2024 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Rough | 2/13/2024 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 2/13/2024 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 2/15/2024 | Corrections Issued | MISAEL ESPARZA |
| Wood Frame | 2/15/2024 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/17/2024 | No Access for Inspection | MICHEL ABAJAN |
| Green Building Rough | 2/17/2024 | No Access for Inspection | MICHEL ABAJAN |
| Insulation | 2/17/2024 | No Access for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 2/17/2024 | No Access for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/21/2024 | Partial Inspection | MISAEL ESPARZA |
| Green Building Rough | 2/21/2024 | Partial Inspection | MISAEL ESPARZA |
| Insulation | 2/21/2024 | Partial Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 2/21/2024 | Partial Inspection | MISAEL ESPARZA |
| Shower Pan | 2/21/2024 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/23/2024 | Approved | JUAN VALENZUELA |
| Green Building Rough | 2/23/2024 | Approved | JUAN VALENZUELA |
| Insulation | 2/23/2024 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 2/23/2024 | Approved | JUAN VALENZUELA |
| Rough-Elec/Plmb/HVAC | 2/23/2024 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 2/27/2024 | Approved | MISAEL ESPARZA |
| Final | 6/4/2024 | OK to Issue CofO | JUAN VALENZUELA |
| Green Building Final | 6/4/2024 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 6/4/2024 | SGSOV Approved | JUAN VALENZUELA |
| Smoke Detectors | 6/4/2024 | Approved | JUAN VALENZUELA |