5254-5256 N ALLOTT AVE 91401

Certificate Information: 5254-5256 N ALLOTT AVE 91401

Application / Permit
23016-20000-39800
Plan Check / Job No.
B23VN15593
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 27'11" X 19' IRREGULARLY SHAPED ATTACHED GARAGE (318 SF) AND (E) 11'11" X 10'9" IRREGULARLY SHAPED PORTION OF SFD (84 SF) TO (N) JUNIOR ACCESSORY DWELLING UNIT (403 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22. WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 11/21/2023
Issuing Office
Current Status
CofO Issued on 6/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2023 APPLICANT
Assigned to Plan Check Engineer 11/16/2023 JEROME MAGAT PALMA
Corrections Issued 11/17/2023 JEROME MAGAT PALMA
Issued 11/21/2023 APPLICANT
Building Plans Picked Up 11/21/2023 APPLICANT
CofO in Progress 6/4/2024 JUAN VALENZUELA
CofO Issued 6/4/2024 RUBEN SALAS
Permit Finaled 6/4/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/17/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 11/17/2023 COLIN LOREDO
Sewer availability Cleared 11/17/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/29/2024 Conditional Approval MISAEL ESPARZA
Footing/Foundation/Slab 1/29/2024 Approved MISAEL ESPARZA
Underground Mechanical 1/29/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 1/31/2024 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 2/13/2024 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 2/13/2024 Approved JUAN VALENZUELA
Green Building Rough 2/13/2024 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 2/13/2024 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 2/13/2024 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 2/15/2024 Corrections Issued MISAEL ESPARZA
Wood Frame 2/15/2024 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 2/17/2024 No Access for Inspection MICHEL ABAJAN
Green Building Rough 2/17/2024 No Access for Inspection MICHEL ABAJAN
Insulation 2/17/2024 No Access for Inspection MICHEL ABAJAN
PLUMBING-Rough 2/17/2024 No Access for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 2/21/2024 Partial Inspection MISAEL ESPARZA
Green Building Rough 2/21/2024 Partial Inspection MISAEL ESPARZA
Insulation 2/21/2024 Partial Inspection MISAEL ESPARZA
PLUMBING-Rough 2/21/2024 Partial Inspection MISAEL ESPARZA
Shower Pan 2/21/2024 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 2/23/2024 Approved JUAN VALENZUELA
Green Building Rough 2/23/2024 Approved JUAN VALENZUELA
Insulation 2/23/2024 Approved JUAN VALENZUELA
Interior/Exterior Lathing 2/23/2024 Approved JUAN VALENZUELA
Rough-Elec/Plmb/HVAC 2/23/2024 Approved JUAN VALENZUELA
Drywall Nailing 2/27/2024 Approved MISAEL ESPARZA
Final 6/4/2024 OK to Issue CofO JUAN VALENZUELA
Green Building Final 6/4/2024 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 6/4/2024 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 6/4/2024 Approved JUAN VALENZUELA