2637 S SEVERANCE ST 90007

Certificate Information: 2637 S SEVERANCE ST 90007

Application / Permit
23016-20000-39793
Plan Check / Job No.
B23VN15589
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
EPLAN: Replace existing wood siding of (E) Apartment building with new Hardie siding. Paint new siding to match existing building color.
Permit Issued
Issued on 6/4/2024
Issuing Office
Current Status
Permit Finaled on 11/25/2024

Permit Application Status History

Submitted 12/8/2023 APPLICANT
Assigned to Plan Check Engineer 12/8/2023 GURUNATH NESARAJAH
Corrections Issued 12/9/2023 GURUNATH NESARAJAH
Plan Check Approved 2/19/2024 GURUNATH NESARAJAH
Issued 6/4/2024 APPLICANT
Permit Finaled 11/21/2024 ALFREDO LOPEZ

Permit Application Clearance Information

ZA Case Cleared 1/24/2024 RYAN LY
Redevelopment Project Area Cleared 2/13/2024 DAVID URITA

Contact Information

Architect Fortunes,, James Louis; Lic. No.: C16792 2240 SARAH COURT      SIGNAL HILL, CA 90755
Contractor Snyder Langston Llc; Lic. No.: 1019188-B       ,
Contractor Snyder Langston Residential, Llc; Lic. No.: 1019188-B       ,

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/10/2024 Partial Inspection ALFREDO LOPEZ
Wood Frame 6/21/2024 Partial Approval ALFREDO LOPEZ
Drywall Nailing 6/26/2024 Not Ready for Inspection ALFREDO LOPEZ
Drywall Nailing 6/28/2024 Partial Approval ALFREDO LOPEZ
Pre-Inspection 7/2/2024 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 7/24/2024 Approved ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 8/2/2024 SGSOV Not Required ALFREDO LOPEZ
Final 8/16/2024 Partial Inspection ALFREDO LOPEZ
Smoke Detectors 8/16/2024 Not Ready for Inspection ALFREDO LOPEZ
Final 8/21/2024 Not Ready for Inspection ALFREDO LOPEZ
Smoke Detectors 8/21/2024 Not Ready for Inspection ALFREDO LOPEZ
Drywall Nailing 8/22/2024 Not Ready for Inspection ALFREDO LOPEZ
Final 8/27/2024 Not Ready for Inspection ALFREDO LOPEZ
Smoke Detectors 8/27/2024 Not Ready for Inspection ALFREDO LOPEZ
Drywall Nailing 8/29/2024 Not Ready for Inspection ALFREDO LOPEZ
Pre-Inspection 9/13/2024 Partial Approval ALFREDO LOPEZ
Final 10/25/2024 Conditional Approval ALFREDO LOPEZ
Smoke Detectors 10/25/2024 Approved ALFREDO LOPEZ
Final 11/12/2024 Conditional Approval ALFREDO LOPEZ
Final 11/21/2024 Permit Finaled ALFREDO LOPEZ