6706 N ALCOVE AVE 91606

Certificate Information: 6706 N ALCOVE AVE 91606

Application / Permit
23016-20000-39733
Plan Check / Job No.
B23VN15545
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Convert (E) Detached garage into and ADU and addition to ADU to build ADU. Per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 5/9/2024
Issuing Office
Current Status
CofO in Progress on 6/26/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/29/2023 APPLICANT
Assigned to Plan Check Engineer 12/1/2023 ALFREDO JARA
Corrections Issued 12/2/2023 ALFREDO JARA
Applicant returned to address corrections 3/13/2024 ALFREDO JARA
Applicant returned to address corrections 3/30/2024 ALFREDO JARA
Applicant returned to address corrections 5/1/2024 JOHNPAUL ISIP
Plan Check Approved 5/6/2024 JOHNPAUL ISIP
Issued 5/9/2024 APPLICANT
CofO in Progress 6/26/2026 WAYNE REGESTER

Permit Application Clearance Information

Address approval Cleared 2/26/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 2/26/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 4/23/2024 ROSE MARIE SMITH
Sewer availability Cleared 4/23/2024 ROSE MARIE SMITH
Construction near power lines Cleared 4/29/2024 WALTER RAMIREZ
Construction within easement Cleared 4/29/2024 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/24/2024 Partial Approval JACK KARGODORIAN
Underground Mechanical 5/24/2024 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 6/18/2024 Not Ready for Inspection GREGG CUMMINGS
Underground Mechanical 6/18/2024 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 7/19/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 8/1/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 9/4/2024 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 9/4/2024 Approved CHRISTOPHE COCHRAN
Green Building Rough 9/4/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Shower Pan 10/9/2025 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 3/27/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Final 3/27/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Footing/Foundation/Slab 3/27/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Green Building Final 3/27/2026 Not Ready for Inspection GAREN HAYRAPETYAN
Green Building Rough 3/27/2026 Not Ready for Inspection GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 3/27/2026 SGSOV Not Ready GAREN HAYRAPETYAN
Smoke Detectors 3/27/2026 Not Ready for Inspection GAREN HAYRAPETYAN
BUILDING-Rough-Frame 5/26/2026 Approved WAYNE REGESTER
Drywall Nailing 5/26/2026 Approved WAYNE REGESTER
Final 5/26/2026 Not Ready for Inspection WAYNE REGESTER
Footing/Foundation/Slab 5/26/2026 Approved WAYNE REGESTER
Green Building Final 5/26/2026 Not Ready for Inspection WAYNE REGESTER
Green Building Rough 5/26/2026 Approved WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 5/26/2026 SGSOV Not Required WAYNE REGESTER
Smoke Detectors 5/26/2026 Approved WAYNE REGESTER
ELECTRICAL-Final 6/25/2026 Approved WAYNE REGESTER
Final 6/25/2026 OK to Issue CofO WAYNE REGESTER
Green Building Final 6/25/2026 Approved WAYNE REGESTER
HVAC-Final 6/25/2026 Approved WAYNE REGESTER
PLUMBING-Final 6/25/2026 Approved WAYNE REGESTER