11680-11682 W HATTERAS ST 91601
Certificate Information: 11680-11682 W HATTERAS ST 91601
- Application / Permit
- 23016-20000-39582
- Plan Check / Job No.
- B23VN15498
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT ATTACHED GARAGE AND LAUNDRY ROOM TO ACCESSORY DWELLING UNIT (11682 W HATTERAS ST) PER LAMC 12.22 A.33(c) and (e). SEE COMMENTS.
- Permit Issued
- Issued on 11/29/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 11/17/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 11/21/2023 | APPLICANT |
| Plan Check Approved | 11/29/2023 | JEROME MAGAT PALMA |
| Issued | 11/29/2023 | APPLICANT |
| CofO in Progress | 5/21/2024 | CHRISTOPHER ROJAS |
| Permit Finaled | 7/2/2024 | RUBEN SALAS |
| CofO Issued | 7/2/2024 | RUBEN SALAS |
| Permit Finaled | 7/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/25/2023 | BRYAN GODINEZ |
| Sewer availability | Cleared | 11/25/2023 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/27/2023 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/13/2023 | Partial Inspection | JOHN COLEMAN |
| Deputy Drilled-In Anchors | 12/19/2023 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 12/20/2023 | Not Ready for Inspection | KIRK SANDERS |
| Footing/Foundation/Slab | 12/20/2023 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 12/27/2023 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2024 | Not Ready for Inspection | KIRK SANDERS |
| Wood Frame | 1/26/2024 | No Access for Inspection | JOHN COLEMAN |
| Wood Frame | 1/30/2024 | Corrections Issued | KIRK SANDERS |
| Deputy Wood Construction | 1/31/2024 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 2/6/2024 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 2/14/2024 | Partial Approval | KIRK SANDERS |
| Interior/Exterior Lathing | 2/14/2024 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 2/26/2024 | Approved | KIRK SANDERS |
| Insulation | 3/1/2024 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/6/2024 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 3/6/2024 | Approved | KIRK SANDERS |
| Green Building Rough | 3/6/2024 | Approved | KIRK SANDERS |
| HVAC-Rough | 3/6/2024 | Approved | KIRK SANDERS |
| Insulation | 3/11/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Insulation | 3/12/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Insulation | 3/18/2024 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/21/2024 | Partial Approval | KIRK SANDERS |
| Drywall Nailing | 3/21/2024 | Partial Approval | KIRK SANDERS |
| Insulation | 3/21/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/27/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2024 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 4/1/2024 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 4/4/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 4/4/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 5/15/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 5/15/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 5/15/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 5/15/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 5/15/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 5/20/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 5/20/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Final | 5/20/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 5/20/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 5/20/2024 | Approved | CHRISTOPHER ROJAS |